By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

  1. Acceleration.
  2. Production output.
  3. Productivity loss.
  4. Productivity efficiency.

Answer(s): C



The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.

  1. Estimate at completion (EAC)
  2. Budget at completion (BAC)
  3. Budgeted cost of work performed (BCWP)
  4. Budgeted cost of work scheduled (BCWS)

Answer(s): B



Budgeted cost of work scheduled is _______________________.

  1. The value of the completed work expressed in terms of the budget assigned to that work
  2. The total authorized budget for accomplishing the project scope
  3. The expected total cost of an activity, group of activities or the project
  4. The sum of all budgets for work scheduled to be accomplished within a given time period

Answer(s): C



Estimate to complete (ETC) is __________________.

  1. The expected remaining cost needed to complete an activity, group of activities or the project
  2. The costs actually incurred in accomplishing the work performed
  3. The expected total cost of an activity, group of activities or the project
  4. The value of the completed work expressed in terms of the budget assigned to that work

Answer(s): A