____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.
Answer(s): C
____________is defined as the earned work hours or dollars for all accounts divided by the budgeted work hours or dollars for all accounts.
Answer(s): A
_____________is defined as the budget for the cost (work) account times the percent complete for that account.
Answer(s): D
____________ is defined as covering work whose component activities are less defined and whose interrelationships are conditional.
Post your Comments and Discuss AACE International CCP exam with other Community members: