A team lead needs to regularly report on the adherence of budget and timeline of a group of projects.

What should the team lead use to organize these projects to allow them to be tracked together?

  1. Layout template
  2. Program
  3. Group

Answer(s): B

Explanation:

In Workfront, a "Program" is used to group related projects that share a common objective or need to be tracked together, such as adherence to budget and timeline. Programs allow for collective reporting on these projects, making it easier for team leads to monitor progress, manage resources, and report on key performance indicators (KPIs) across multiple projects.



A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.
How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

  1. Share the program with Program Manager A with Manage access and ensure the system administrator adjusts Program Manager A's access level.
  2. Share the program with Program Manager A with Manage access and ensure Program Manager A understands they cannot manage the rest of the portfolio.
  3. Share the program with Program Manager A with Manage access and remove Program Manager A's Manage access on the portfolio.

Answer(s): C

Explanation:

In Workfront, when adjusting user access, it's important to ensure that Program Manager A only has the necessary level of access to their own program. To rectify the over-access issue, the portfolio manager must share the relevant program with Program Manager A with the correct Manage access and remove their broader Manage access to the portfolio. This restricts their control to only their specific program.



The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.
Which task settings need to be configured to meet these requirements?

  1. The Task Constraint should be set to Must Start On with Planned Time set to 2 weeks and Duration set to 10 hours.
  2. The Task Constraint should be set to Must Start On with Planned Hours set to 10 hours and
    Duration set to 2 weeks.
  3. The Task Constraint should be set to Start Date of September 23 with Planned Hours set to 10 hours and Issue Duration set to 2 weeks.

Answer(s): B

Explanation:

In Workfront, setting the correct task constraint and planned hours ensures that the task starts on the intended date (September 23) and allows the team to track the time allocated (10 hours) over a 2- week duration. "Must Start On" ensures the task begins exactly on the planned start date.



A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days?

  1. Change the Task Duration Type to Effort Driven
  2. Change the Task Duration Type to Calculated Work
  3. Change the Task Constraint to Fixed Dates
  4. Change the Task Constraint to As Soon As Possible

Answer(s): B

Explanation:

When reducing the task duration and distributing the work among multiple users, changing the Task Duration Type to "Calculated Work" allows Workfront to automatically adjust the duration based on the number of assignees (in this case, 4 users). This will enable the task to be completed within the new shorter timeframe without adjusting the total planned hours.