To whom or what would a project owner assign a task so the task is visible in a Scrum or Kanban backlog?

  1. A user that has access to a burndown
  2. A job role labeled as Agile User
  3. A team marked as an agile team

Answer(s): C



Which date type should an assignee update to change the completion date of a task?

  1. Actual Completion Date
  2. Commit Date
  3. Planned Completion Date
  4. Projected Start Date

Answer(s): C

Explanation:

In Workfront, to update the planned completion of a task, the assignee should modify the "Planned Completion Date." This date is used for scheduling and planning purposes to track when the task is expected to be finished. Changing the "Planned Completion Date" adjusts the task's projected timeline and allows for a recalculation of project dependencies.



A company expects managers to complete a Workfront Business Case and submit it to the Project Sponsor for approval before a project enters Planning status.
What Workfront process will effectively facilitate the Project Sponsor review?

  1. Request Approval Process
  2. Request Submission Process
  3. Project Submission Process
  4. Project Approval Process

Answer(s): B

Explanation:

In Workfront, the "Request Submission Process" is used when a formal submission is required for review before the project proceeds to the planning phase. This process ensures that all necessary documentation, such as the business case, is completed and submitted to the sponsor for approval, streamlining the review process.



Given this information regarding a Task:
· Planned Start Date: May 14
· Actual Start Date: May 14
· Planned Completion Date: May 20
· Projected Completion Date: May 22
· Percent Complete: 50%

· Duration: 5 Days
· Planned Hours: 8 Hours
· Status: In Progress
If today's date were May 19, what would be the Task's progress status?

  1. Behind
  2. On Time
  3. At Risk

Answer(s): C

Explanation:

In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as "At Risk." This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.



The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

  1. Start No Later Than
  2. Must Start On
  3. As Late As Possible

Answer(s): C

Explanation:

In Workfront, the "As Late As Possible" task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.



Viewing page 7 of 15
Viewing questions 31 - 35 out of 70 questions