When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?

  1. Add a custom form
  2. Attach a template to the project
  3. Add tasks

Answer(s): A

Explanation:

In Workfront, users with "Contribute" access are typically able to modify and interact with content but are not allowed to perform higher-level administrative tasks like attaching templates or adding tasks. Adding a custom form is within the scope of what a user with Contribute access can do, as it involves adding data input fields to an existing project.



An organization has created unique data fields relevant to their projects. Starting by navigating from a project's landing page, where is this data found?

  1. Project Details > Custom Forms
  2. Project Details > Overview
  3. Business Case > Project Info

Answer(s): C

Explanation:

In Workfront, custom data fields created for projects are typically found within the "Business Case" section, specifically under "Project Info." This area houses key project information and unique custom fields that are relevant to the project's setup. The "Project Details" section is more focused on task-related information and the overall summary of the project.



A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.
Which action should the stakeholder take to log the risk?

  1. Log a risk as part of the project business case and identify it as a "schedule" risk.
  2. Log an issue on the project and explain that the completion date is at risk.
  3. Create a task in the project and set the Planned Completion Date for 2 weeks.

Answer(s): A

Explanation:

In Adobe Workfront, risks associated with a project should be logged as part of the project business case. The "Risk" section within the business case allows stakeholders to document any potential threats to the project timeline, scope, or resources. Identifying this risk as a "schedule" risk helps communicate the potential delay to the project stakeholders and allows it to be tracked and mitigated effectively.



A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.
What impact does this have on the project progress status?

  1. The next team member cannot start his task.
  2. No impact as the task is not overdue.
  3. The project shows an At Risk automatic condition.

Answer(s): C

Explanation:

In Workfront, if a task that is part of the critical path is delayed, it affects the overall project schedule. Even though the task is not overdue yet, Workfront's automated system flags the project as "At Risk" if there is a delay in progress that could impact the project's timeline. This "At Risk" condition acts as a warning to project managers and stakeholders that immediate attention is needed.