[Inspection and Testing Requirements]
Which of the following is the appropriate term for testing refractory that was sampled during project site installation in order to confirm that it meets specified physical property standards?

  1. Hammer testing
  2. Pre-qualification testing
  3. As-installed testing
  4. Visual testing

Answer(s): C



[Material Requirements]
The quantity of manufactured refractory that has the same formulation as that prepared in an uninterrupted manufacturing operation is called a:

  1. pallet
  2. test sample
  3. production run
  4. bag

Answer(s): C



[Inspection and Testing Requirements]
Which of the following is a quality control element?
(This may have more than one correct answer; please select all answers that apply.)

  1. As-installed testing
  2. Initial Inspection
  3. Installation monitoring
  4. Report writing

Answer(s): A,B,C



[Installation Procedures]
If the refractory lining is required before pressure testing, all pressure-retaining welds shall:

  1. be lined with coal tar epoxy.
  2. include additional anchors.
  3. remain unlined and exposed to test medium.
  4. be gunned with no needles.

Answer(s): C



[Material Requirements]
When water is used for refractory installed on a carbon steel surface with a stainless steel anchorage, the chloride content of the potable water shall not exceed:

  1. 50 ppm
  2. 100 ppm
  3. 200 ppm
  4. 250 ppm

Answer(s): A



Viewing page 4 of 18
Viewing questions 16 - 20 out of 85 questions


Post your Comments and Discuss API API-936 exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!