Every operation producing a product or service is a series of linked processes and each process has a specific capacity to produce the given defined output for the operation, this is called:

  1. Theory of constraints
  2. Managing constraints
  3. Drum-Buffer-Rope
  4. Scheduling Bottlenecks

Answer(s): A



Find methods to maximize the utilization of the constraint toward productive throughput is called:

  1. Utilize constraint
  2. Manage constraint
  3. Exploit constraint
  4. None of the above

Answer(s): C



Means to find ways to increase the available hours of the constraint, including more of it is referred to as:

  1. Elevate constraint
  2. Subordinate constraint
  3. Identify constraint
  4. All of the above

Answer(s): A



What represents the master schedule for the operation, which is focused around the pace of throughput as defined by the constraint?

  1. Drum
  2. Buffer
  3. Rope
  4. None of the above

Answer(s): A



Which four primary plant types are defined, and they are used to specify the flow of materials through a production process?

  1. I-plant, A-plant, B-plant, G-Plant
  2. I-plant, A-plant, V-plant, T-Plant
  3. C-plant, K-plant, B-plant, S-Plant
  4. A-plant, D-plant, B-plant, F-Plant

Answer(s): B