To decrease time to market for discrete products, it is most effective to improve which of the following phases?

  1. Product definition
  2. Product design
  3. Production
  4. Distribution

Answer(s): B



Reducing design cycle time improves which of the following measures?

  1. Production throughput
  2. Return on investment (ROI)
  3. Manufacturability
  4. Quality

Answer(s): B



To reduce the cost of transaction processing, a repetitive manufacturer first would implement:

  1. inventory staging.
  2. a point-of-sale system.
  3. point-of-use storage.
  4. cycle counting.

Answer(s): C



The next job to be performed was selected because it had the least amount of operation time prior to the due date. Which of the following priority sequencing rules was being used?

  1. Slack time per operation
  2. Shortest operation time
  3. Critical ratio
  4. Slack time per order

Answer(s): B



Control charts are used to do which of the following?

  1. Determine preventative maintenance schedules
  2. Display variation of the production process
  3. Determine the percentage of output within specification limits
  4. Verify ongoing process capability

Answer(s): B