When initially creating MoSCoW priorities, what is the primary focus?

  1. Project priorities
  2. Project increment priorities
  3. Timebox priorities
  4. Iterative Development priorities

Answer(s): A



Which of the following is a DSMD principle?

  1. Build incrementally from firm foundations
  2. Build incrementally from Feasibility onwards
  3. Build incrementally in Timeboxes
  4. Build incrementally

Answer(s): A



Identify the missing words in the following sentence.

Principles 1 ­Focus on the Business Need suggests that every decision taken during a project should be [?] ­ to deliver what the business needs to be delivered.

  1. The responsibility of the Business Sponsor
  2. Share between all of the project roles
  3. Viewed in light of the overriding project goal
  4. Made collaboratively

Answer(s): D



Which statement about DSDM roles is true?

  1. In DSDM, one person must hold several roles
  2. One DSDM roles does NOT necessarily mean one person
  3. All DSDM roles should be shared
  4. DSDM roles should NOT be split between two people

Answer(s): B



During what phase should the strategy for Iterative Development be considered?

  1. Pre-Project
  2. Feasibility
  3. Foundations
  4. Evolutionary Development

Answer(s): C



Viewing page 4 of 11
Viewing questions 16 - 20 out of 150 questions