Free AgilePM-Practitioner Exam Braindumps
Agile Project Management (AgilePM) Practitioner Questions 31–35 (page: 8)

Updated On: 10-Feb-2026
View Related Case Study

Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?

  1. Accustomed to bringing in contract staff for short periods of time.
  2. Closely manages the building team so that they consistently produce high-quality work.
  3. Is able to represent the team in all daily meetings.
  4. An experienced builder who is good at turning a brief into a practical design.
  5. Is empowered by Timber Tigers' management to make decisions on the building work.

Answer(s): B,D



View Related Case Study

The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and to know who should be where. Some of the contractors have started to turn up late to the site.

Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.

Answer the following questions about motivating the contractor teams according to Agile Project Management.

How should the Project Manager encourage the resources to operate more successfully?

  1. Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan.
  2. Hold a separate Daily Stand-up meeting for contractors only.
  3. Provide a detailed plan of activity for each contractor team.
  4. Schedule the electrical and plumbing teams so that they work on different Timeboxes.

Answer(s): A



View Related Case Study

How should the Project Manager encourage the contractors to turn up on time?

  1. Place a penalty clause on all contractors for late arrival.
  2. Appoint Team Leaders to each of the electrical and plumbing teams.
  3. Encourage open and honest communication to re-establish an environment of trust.
  4. Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.

Answer(s): C



View Related Case Study

How should the Project Manager assist the plumbers to deliver the plumbing?

  1. Split the entire Solution Development Team into smaller teams covering specific locations of the house.
  2. Decide on the location of the radiators on behalf of Architecture Angels.
  3. Establish an inter-team competition to see which team can complete first.
  4. Approve each Timebox before work continues in the next.

Answer(s): A



View Related Case Study

How should the Project Manager assist the electricians to deliver the wiring?

  1. Provide separate electricians' rooms so they can focus on their work.
  2. Hold a weekly meeting for electricians so they can report on progress.
  3. Encourage the Business Ambassador to be available to discuss location of electrical sockets.
  4. Produce a detailed design of all electrical socket locations, to be approved by the Technical Co- ordinator.

Answer(s): C



Viewing page 8 of 28
Viewing questions 36 - 40 out of 184 questions