At the end of the third week of a project, the actual cost of work performed is $7000 USd and the budgeted cost of work performed is $8000 USd. Which of the following is true?

  1. The project is under budget.
  2. The project is budget incorrect.
  3. The project has been back-end loaded.
  4. The project is over budget.

Answer(s): A



Which of the following does NOT describe one of the four main types of specifications?

  1. Based on an established standard
  2. Focused on exact properties and installation methods
  3. Calling out brand names and models
  4. Focusing on the desired results
  5. Listing maximum acceptable performance

Answer(s): E



At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?

  1. The project is ahead of schedule.
  2. The project is over budget.
  3. The project is behind schedule.
  4. The project is under budget.

Answer(s): A



Which is NOT a type of contract?

  1. Contractor submits a fixed price for the SOW
  2. Contractor is reimbursed for actual costs plus a fee
  3. Unit price is used because the SOW cannot be determined prior to bid
  4. Mediation panel assigns a fair price based on work completed

Answer(s): D



A work breakdown structure is:

  1. Influenced by market conditions at the time of the project execution
  2. A set of accounting codes
  3. Reflective of project organizational structure
  4. Easily standardized
  5. A replacement for a Gantt chart

Answer(s): A