A scope of work should contain all of the following EXCEPT:

  1. Request for purchase
  2. Project schedule
  3. Project objective
  4. Assumptions
  5. Customer needs

Answer(s): A



Which area of project management covers the blending of various subteams into a project organization with a cohesive plan?

  1. Integration management
  2. Human resources management
  3. Risk management
  4. Communications management

Answer(s): A



All of the following are considered market or regional conditions that can impact construction costs EXCEPT:

  1. Displacement and relocation
  2. Construction time frame
  3. Other large projects in the area
  4. Seasonal effects on construction costs

Answer(s): A



Select the appropriate task to complete section 2.2 of the work breakdown structure (WBS) below:

2 Technician

2.1 Install cabling

2.2 __________

2.3 Activate wireless

  1. Install access point
  2. Clean work area
  3. Install pathway for cabling
  4. Confirm wireless coverage

Answer(s): A



What is the PERT estimate of time for cable placement on a given job?

- Optimistic time is 100 hours

- Most likely time is 125 hours

- Pessimistic time is 210 hours

  1. 100 hours
  2. 125 hours
  3. 135 hours
  4. 155 hours
  5. 175 hours

Answer(s): C