Free RCDD-002 Exam Braindumps
BICSI Registered Communications Distribution Designer - RCDD Questions 197–201 (page: 34)

Updated On: 9-Feb-2026

Select the appropriate task to complete the section 2.2 of the work breakdown structure below:

2. Technician

2.1 Install rack

2.2 _________

2.3 Place fiber

2.4 Terminate fiber

2.5 Test fiber

  1. Prepare as-built drawings
  2. Install connector housing
  3. Clean/polish connectors
  4. Specify fiber

Answer(s): B



What is the PERT estimate (in hours) for project design where:

- Optimistic time is 40 hours

- Most likely time is 50 hours

- Pessimistic time is 60 hours

  1. 40 hours
  2. 45 hours
  3. 50 hours
  4. 55 hours
  5. 60 hours

Answer(s): C



Which is NOT true about conformance quality?

  1. It focuses on physical quality.
  2. It involves evaluating customer satisfaction.
  3. It requires work force training.
  4. It includes inspections of work.
  5. It follows the principle of plan, do, check, and act.

Answer(s): B



Exhibit:



The figure below represents what type of chart?

  1. Milestone
  2. PERT
  3. Gantt
  4. Calendar
  5. Status

Answer(s): A



Exhibit:



If a work breakdown structure (WBS) shows the tasks below, what is C, the successor task?

A) Install OSP pathways

B) Install fiber

C) ________.

  1. Hold inspection
  2. Create budget
  3. Conduct safety meeting
  4. Perform site survey

Answer(s): A



Viewing page 34 of 74
Viewing questions 166 - 170 out of 361 questions


Post your Comments and Discuss BICSI RCDD-002 exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!