Free L4M3 Exam Braindumps (page: 6)

Page 6 of 48

Southwark is negotiating a contract with Orchard to provide software and IT services. Orchard will manufacture and install the products which are contractually supplied by IBM. Southwark's procurement manager is worried that during the contract there would be some problems that they would not able to claim for damages from Orchard.
Which of the following should be included in the head contract so that Southward can sue IBM, should the need arise?

  1. Negligence
  2. Indemnity
  3. Collateral warranty deed
  4. Insurance

Answer(s): C

Explanation:

A Collateral Warranty is a contract under which a consultant, a building contractor or a sub- contractor warrants to a third party that is has fulfilled its obligations under its professional appointment, building contract or sub-contract. The purpose of a Collateral Warranty is to give a third party, who is not a party to the original contract, rights to enforce that original contract. In this case, IBM is the subcontractor, then purchaser can use collateral warranty deed to bind them.


Reference:

- Collateral Warranties ­ an Overview
- CIPS study guide page 39-40 LO 1, AC 1.2



In a contract, both buyer and supplier agreed the lead time is 3 days. The contract also requires that any variation must be made in writing. Then the buyer places an order by phone call and requests delivery the next day, but the supplier delivers on the third day since the order. Can buyer refuse to pay as supplier did not deliver per time?

  1. No, the supplier delivers within a reasonable time
  2. Yes, late delivery is a force majeure event
  3. Yes, the supplier has breached the contract
  4. No, supplier has shortened lead time to 1 day

Answer(s): A

Explanation:

Lead time is the amount of time that passes from the start of a process until its conclusion. In procurement, lead time can be understood as the amount of time that passes from placing an order until the delivery.
In the scenario, the contract requires the supplier to make a delivery within 3 days since the order. This contract can only be amended with written consent from both parties. Therefore, there is no ground for shortening the lead time to 1 day because the new lead time is only the request of buyer. Then the supplier still makes delivery within agreed lead time. LO 1, AC 1.1



Which of the following are reasons why a purchaser wants to embed a subcontracting clause into the main contract? Select TWO that apply:

  1. To induce the conflicts between the main contractor and subcontractors
  2. To improve supply chain transparency
  3. To reduce the main contract complexity
  4. To keep main contractor liable
  5. To condemn whole liabilities to subcontractors

Answer(s): D

Explanation:

There are number of reasons why the purchaser will want to control the supplier's subcontracting:
- Supply chain transparency: Normally the purchaser has invested a lot of effort into selecting the right contractor. However, the main contractor's selection of subcontractor might not be in such careful manner, which may result in poor performance. Purchaser must know who subcontractors are. Controlling the subcontracting process can help the purchaser control the outcome.

- Contract terms: the purchaser's requirements must be reflected in the subcontracts. The subcontracting clauses may require the main contractor to do this.
- Liability: the main contractor may subcontract the whole or a part of its liabilities. Subcontracting clause may bind the contractor to be liable with the work, it cannot just blame the subcontractor for any faults.


Reference:

CIPS study guide page 154-155 LO 3, AC 3.2



In a sale contract, a clause requires the seller to "defend, reimburse, and hold harmless" the buyer and its personnel from and against any and all damages arising in connection with some specific circumstances. This clause is an example of...?

  1. Insurance
  2. Liquidated damages
  3. Indemnity
  4. Force Majeure

Answer(s): C

Explanation:

An indemnity is a promise by one party to compensate another for the loss suffered as a consequence of a specific event, called the ''trigger event''. The trigger event can be anything defined by the parties, including:
- A breach of contract;
- A party's fault or negligence;
- A specific action.
An indemnity operates as a transfer of risks between the parties, and changes what they would otherwise be liable for or entitled to under a normal damage claim. Force Majeure Provisions: A force majeure event refers to the occurrence of an event which is outside the reasonable control of a party and which prevents that party from performing its obligations under a contract.
Liquidated damages are presented in certain legal contracts as an estimate of otherwise intangible or hard-to-define losses to one of the parties. It is a provision that allows for the payment of a specified sum should one of the parties be in breach of contract. LO 3, AC 3.2



Page 6 of 48



Post your Comments and Discuss CIPS L4M3 exam with other Community members:

Tina commented on September 20, 2024
I need to emphasis that this exam is extremely HARD! So prepare well or else you will fail. I got lucky and passed mine. But I used these dumps and some other sources.
Singapore
upvote

Evangelista commented on June 30, 2024
the questions assist me to read and understand the material
UNITED KINGDOM
upvote

Leungoinalame Gobuiwang commented on May 01, 2024
That was good questions to explore on
BOTSWANA
upvote

Leungoinalame Gobuiwang commented on May 01, 2024
It bid challenging but I think I can manage
BOTSWANA
upvote

Leungoinalame Gobuiwang commented on May 01, 2024
I think the L4M3 it needs a person to read to understand
BOTSWANA
upvote

Rudasingwa Innocent commented on March 13, 2024
This prepares good managers for procurement
Anonymous
upvote

Rudasingwa Innocent commented on March 13, 2024
This is good since it prepares the future managers for procurement.
Anonymous
upvote