In just in time production system, when is an upstream production triggered?

  1. When the inventory level reaches the reorder point
  2. After the management team forecasts the future demands
  3. When downstream operations summon the upstream production
  4. When the production workers are idle

Answer(s): C

Explanation:

Along with Jidoka, Just-in-time (JIT) production is one of the pillars of the two Toyota Production System. It is a production method that fundamentally changed the way large-scale production oc- curred in the 20th century, and is the basis for Lean Manufacturing (Lean for short), which is the school of thought many modern companies have modeled themselves after. JIT production is often called a pull system because instead of using traditional push production where scheduling is done based on historical data and demand forecasting, production is scheduled based on actual customer orders. Rather than predicting demands from customers, the JIT method requires that actual customer demand exists. Production doesn't begin before an order triggers it. This system not only reduces the amount of extra inventory, but also reduces the amount of work in progress at one time.


Reference:

- Just-in-Time Production
- CIPS study guide page 122-127
LO 2, AC 2.3



Manufacturing resources planning (MRP II) was developed from material requirement planning (MRP).
Which of the following is the additional input that is available in MRP II but does not ap-pear in MRP?

  1. Finance
  2. Bill of materials
  3. Master production schedule
  4. Inventory records

Answer(s): A

Explanation:

MRP I was some of the first business software to be widely adopted during the 1970s. Manufacturers sought these systems in order to improve efficiency and accuracy when it came to basic processes such as production scheduling and inventory management. By the 1980s, manufacturers realized they needed software that could also tie into their accounting systems and forecast inventory requirements. Enter MRP II, which included these integrations in addition to all the capabilities offered by MRP I. Enterprise resource planning (ERP) software features--which we'll cover later on--are included in the following table for comparison.


Reference:

- MRP vs. MRP II: What's the Difference?
- CIPS study guide page 118-119
LO 2, AC 2.3



Multiple approval levels for a small purchase request is an example of which type of waste?

  1. Over-processing
  2. Not using talent
  3. Over-production
  4. Inventory

Answer(s): A

Explanation:

Lean thinking aims to remove wastes from work processes. Before diving into the 8 wastes, it is important to understand what waste is. Waste is any action or step in a process that does not add value to the customer. In other words, waste is any process that the customer does not want to pay for.
The original seven wastes (Muda) was developed by Taiichi Ohno, the Chief Engineer at Toyota, as part of the Toyota Production System (TPS). The seven wastes are Transportation, Inventory, Motion, Waiting, Overproduction, Overprocessing and Defects. They are often referred to by the acronym `TIMWOOD'. The 8th waste of non-utilized talent or `Skills' of workers was later introduced in the 1990s when the Toyota Production System was adopted in the Western world. As a result, the 8 wastes are commonly referred to as `TIMWOODS'.



Source: The lean way Multiple approval levels for a small purchase request is an example of over-processing since this adds more unnecessary work to users and procurement professionals.


Reference:

CIPS study guide page 127-129
LO 2, AC 2.3



A pharmaceutical firm offers a new drug called NC-01. After analysing the market, the firm realises that the demand is largely variable. But they still have to forecast the customer demand for the next production cycle. The new drug NC-01 is best described as which type of item?

  1. Dependent demand
  2. Indirect demand
  3. Overhead items
  4. Independent demand

Answer(s): D

Explanation:

Dependent demand is the requirement for stock item which is directly related to and therefore de- pendent upon the rate of production (examples are: raw materials, components, energy) Independent demand is the requirement for stock item which is not directly related to, and is therefore independent of rate of production. Although independent demand is called thus, it can still be influenced by economic factors external to the demand-supply model such as general consumer sentiment and consumers' available disposal income. However, businesses that need to predict the number of products with independent demand needed to sate their customers have it easier than businesses that must calculate the demand for products with dependent demand because there are fewer factors to consider.
In this scenario, the new drug is finished good which is dependent on the demand of the market, and the firm needs to forecast before initiating the production process. The item is independent from rate of production, therefore, it must be independent demand item.


Reference:

CIPS study guide page 95-98
LO 2, AC 2.1



Which of the following is another name for scheduled (routine) maintenance?

  1. Preventative maintenance
  2. Predictive maintenance
  3. Run to breakdown
  4. Corrective maintenance

Answer(s): A

Explanation:

There are different types of maintenance that organizations use to increase the uptime of their assets and utility of their facilities. Based on an organization's budget, amount of resources, level of combined experience, and maintenance goals, one or more maintenance types are used.
Proactive types of maintenance
Preventive maintenance
Preventive maintenance is the most popular type of proactive maintenance. To start conducting preventive maintenance tasks (PMs), an organization does not need to purchase new technology if it already has a CMMS. This is not the case with predictive maintenance which requires condition monitoring sensors and new software integrations. However, with preventive maintenance, the or- ganization runs the risk of over-scheduling maintenance tasks because tasks are scheduled based on time rather than actual conditions. That said, preventive maintenance achieves 12% to 18% cost savings over reactive maintenance.
Predictive maintenance
Predictive maintenance (PdM) is what savvy maintenance teams aspire to have or are already im- plementing. The major barrier to PdM is the time it takes to implement rather than the cost of the technology itself. For instance, a vibration sensor that can identify imbalance, misalignment, and resonance issues only costs around $200. But the time it takes to install, integrate with other maintenance software, and adopt a culture around is not time that all organizations are willing to allocate. For those that do allocate the time, PdM provides an 8% to 12% cost savings over preventive maintenance.
Condition-based maintenance
Condition-based maintenance (CBM) is at the core of predictive maintenance but, on its own, does not rely on technology to determine the condition of an asset like PdM does. For instance, a manager may instruct an operator to monitor the condition of an asset and submit a work request when a specific condition is met. This approach may, or may not be, as reliable as predictive maintenance. An organization that has highly-trained operators may spot hazardous conditions better than an organization using PdM technology that doesn't know what to look for.
Scheduled maintenance
Scheduled maintenance includes work that is scheduled on a calendar for completion. The most common type of scheduled maintenance is calendar-based preventive maintenance tasks. These are scheduled well in advance of completion. For instance, an asset with a monthly PM has twelve instances of scheduled maintenance in a given year. However, just because maintenance is scheduled does not mean it's planned. Planned maintenance implies that a maintenance planner or other type of maintenance worker has fully planned for parts, materials, skills, and other resources to be available during the scheduled time window.

Planned maintenance
Planned maintenance is work that's prepared for in advance of it taking place. According to an UpKeep survey, it's also the most popular key performance indicator (KPI) to track. A high planned maintenance percentage indicates that a maintenance team will have resources available to complete work for the time/day the work is scheduled for. Having a high planned maintenance percentage also helps boost other maintenance KPIs like schedule compliance. More planned maintenance means more successful completion of scheduled maintenance.

Routine maintenance
Routine maintenance is a form of time-based maintenance and preventive maintenance, though some organizations differentiate between routine maintenance and preventive maintenance. They use the latter for smaller tasks (i.e. cleaning) performed at higher frequencies (hourly, daily) and the former for larger tasks (i.e. inspections) performed at lower frequencies (weekly, monthly, annually). Additionally, routine maintenance is performed by operators, janitors, and other staff member while preventive maintenance is performed by technicians. Non-routine maintenance includes maintenance that is performed reactively or only when needed based on an asset's conditions.

Reactive types of maintenance
Emergency maintenance
Emergency maintenance occurs when an asset requires immediate attention in order to keep a facility operational or safe. This is the most reactive and intrusive type of maintenance as it pulls technicians away from other jobs and lowers schedule compliance. In extreme circumstances, emergency maintenance can set an organization back days depending on the scope of the repair, available parts, and the asset's level of importance. To reduce the amount of emergency maintenance that is both unplanned and unscheduled, organizations adopt various forms of proactive maintenance.

Corrective maintenance
Corrective maintenance is inherently part of emergency maintenance because, when there is an emergency, something needs corrected or fixed. In this way, corrective maintenance is mostly reactive. However, it can also be proactive. If an asset with a condition monitoring sensor detects an issue, a work order is created and a technician is sent to correct it. Similarly, preventive maintenance is considered corrective maintenance if there is an issue to fix. This is rare though as PMs are often conducted when an asset is in good working order.
Other types of maintenance
Deferred maintenance
Deferred maintenance includes repairs and inspections that are put into a backlog due to limited budget and resources.
While deferring maintenance saves money up front, the costs of not performing important maintenance compounds at 7% annually. Rising costs come from fines resulting from missed inspections and unscheduled downtime that brings production to a standstill. By far, deferred maintenance and emergency maintenance are the least desired types of maintenance.
Total productive maintenance
Total productive maintenance (TPM) is the broadest type of maintenance that targets more than the assets that need maintained. It also aims to improve employee satisfaction and overall morale in the workplace, specifically in manufacturing plants. TPM does this by increasing overall equipment effectiveness (OEE) and the amount of planned maintenance. More planned work means more workers have the resources they need to do their job, which means higher levels of satisfaction. TPM also leverages machine operators to participate in maintenance and take ownership of their equipment.


Reference:

Types of Maintenance - Upkeep
CIPS study guide page 158-159
LO 3, AC 3.1



Viewing page 13 of 28
Viewing questions 61 - 65 out of 255 questions


Post your Comments and Discuss CIPS L4M7 exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!