Doug is a Manager at ABC Ltd. The company is struggling financially and needs to make several changes to its operating procedures to maintain its position in the marketplace. The changes involve letting 10% of staff go and moving 70% of staff to remote online working instead of being office- based. The staff at ABC have, in general, not taken well to the changes, and motivation has decreased. In order to push through with the changes, Doug has stated that staff who volunteer to work online will receive an additional day of annual leave, and if staff refuse to move to the online system, this will have repercussions on their ability to be promoted within the company. Because of this, all remaining staff have now embraced the changes.
Which two types of influence were used in managing this change process?

  1. Education
  2. Persuasion
  3. Coercion
  4. Reward

Answer(s): C,D

Explanation:

The additional day of annual leave offered to employees who volunteer for online work is a form of reward, while the consequence of not being promoted for those who refuse to move online is an example of coercion. Coercion uses threats or negative consequences to drive compliance, while rewards offer incentives to encourage participation. This aligns with influencing strategies in change management. (


Reference:

p.203 of the study guide).



When should a company use redundancy to implement change? Answer Options:

  1. When reducing overhead costs
  2. When losing business and reducing workload
  3. When shifting organizational culture
  4. When expanding into new markets

Answer(s): C

Explanation:

Redundancy is a strategic tool for cultural change (p.208). Options A & B relate to cost-cutting and downsizing, not change.

Option D involves expansion, not workforce reduction. [P.208]



"Persuasion should be a last resort in cultural change." Is this statement true? Answer Options:

  1. Yes ­ persuasion should be linked to an implicit or perceived threat
  2. Yes ­ persuasion should only be used after coercion has failed
  3. No ­ persuasion should be planned before implementing change
  4. No ­ persuasion is not useful in large cultural shifts

Answer(s): C

Explanation:

Persuasion is one of the best tools for cultural change (p.204). Option A is incorrect--persuasion should not involve threats. **Option B is incorrect--persuasion should be the first approach, not the last. Option D is incorrect--persuasion is highly effective in large-scale change. [P.204]



Which culture type is task-oriented, structured, and uses logic for decisions? Answer Options:

  1. Linear-Active
  2. Multi-Active
  3. Reactive
  4. Proactive

Answer(s): A

Explanation:

A Linear-Active culture (p.176) focuses on logic, organization, and process-based decision-making. Multi-Active (B) focuses on emotions and relationships.

Reactive (C) adapts to external changes.
Proactive (D) anticipates change, but does not define structure. [P.176]



Glitter Kitten Ltd is considering two expansion options. The CEO wants a quick analysis and uses the Payback Method.
Q: What financial metric is the leadership team using for expansion? Answer Options:

  1. Discount rate
  2. Bank rate
  3. Interest rate
  4. Return rate

Answer(s): A

Explanation:

Net Present Value (NPV) calculations require a discount rate (p.1.4). Bank rate (B) relates to loans, not investment decisions. Interest rate (C) applies to borrowing, not profitability.
Return rate (D) is not the main NPV metric. [P.1.4]