Supply Network Design Questions 16–20 (page: 5)

Updated On: 10-Feb-2026

The operations department of ABC Ltd has recently launched a new product. The product is manufactured within a large factory and then sent to retailers for sale. The department has a system in place which details the components required for the product and the quantities required to fulfil customer demand. The system works online and links to other areas of the business including HR and finance.

So far, several large orders have been placed for the product from different retailers. The Chief Operations Officer (COO) has decided to programme the completion of the orders based on when the orders were placed. The benefit of this strategy is that it will give each customer a similar lead time. Thus far no buffer stock has been created as products are only created when orders are received.

Three teams are required to make the product and the product flows from team one to team two to team three, each team adding a component to the product. Unfortunately, team two are short staffed and are completing their work at a slower rate than the other two teams. This is a huge consideration for the COO as it will impact upon the capacity of the organisation.

The retailers have all signed contracts with ABC Ltd and the COO is extremely happy that they are long term contracts. Contract 1 is with retailer X and the price is set for three years. Contract 2 is with retailer Y and is a five year contract where the price will be reviewed annually in line with CPI. Contract 3 has a variable pricing mechanism based on the volume of products ordered.

What system is used by ABC Ltd?

  1. MRP
  2. Lean
  3. ERP
  4. KPI

Answer(s): C

Explanation:

The system used is ERP (Enterprise Resource Planning) since it links multiple business functions such as HR and finance. MRP and MRPII are primarily used for manufacturing/operations, and KPI refers to performance measurement rather than a system. (See LO 3.3)



The operations department of ABC Ltd has recently launched a new product. The product is manufactured within a large factory and then sent to retailers for sale. The department has a system in place which details the components required for the product and the quantities required to fulfil customer demand. The system works online and links to other areas of the business including HR and finance.

So far, several large orders have been placed for the product from different retailers. The Chief Operations Officer (COO) has decided to programme the completion of the orders based on when the orders were placed. The benefit of this strategy is that it will give each customer a similar lead time. Thus far no buffer stock has been created as products are only created when orders are received.

Three teams are required to make the product and the product flows from team one to team two to team three, each team adding a component to the product. Unfortunately, team two are short staffed and are completing their work at a slower rate than the other two teams. This is a huge consideration for the COO as it will impact upon the capacity of the organisation.

The retailers have all signed contracts with ABC Ltd and the COO is extremely happy that they are long term contracts. Contract 1 is with retailer X and the price is set for three years. Contract 2 is with retailer Y and is a five year contract where the price will be reviewed annually in line with CPI. Contract 3 has a variable pricing mechanism based on the volume of products ordered.

What production method is used by ABC?

  1. Earliest due date
  2. First in, first out
  3. Similar process
  4. Shortest processing time

Answer(s): B

Explanation:

The production method is First In, First Out (FIFO) because orders are processed based on when they were received. This method ensures fairness in lead times across different customers. (See LO 3.2)



The operations department of ABC Ltd has recently launched a new product. The product is manufactured within a large factory and then sent to retailers for sale. The department has a system in place which details the components required for the product and the quantities required to fulfil customer demand. The system works online and links to other areas of the business including HR and finance.

So far, several large orders have been placed for the product from different retailers. The Chief Operations Officer (COO) has decided to programme the completion of the orders based on when the orders were placed. The benefit of this strategy is that it will give each customer a similar lead time. Thus far no buffer stock has been created as products are only created when orders are received.

Three teams are required to make the product and the product flows from team one to team two to team three, each team adding a component to the product. Unfortunately, team two are short staffed and are completing their work at a slower rate than the other two teams. This is a huge consideration for the COO as it will impact upon the capacity of the organisation.

The retailers have all signed contracts with ABC Ltd and the COO is extremely happy that they are long term contracts. Contract 1 is with retailer X and the price is set for three years. Contract 2 is with retailer Y and is a five year contract where the price will be reviewed annually in line with CPI. Contract 3 has a variable pricing mechanism based on the volume of products ordered.

What is the nature of the COO's consideration?

  1. Theory of Constraints
  2. Push technique
  3. Variance analysis
  4. Corporate strategy

Answer(s): A

Explanation:

This is an issue related to the Theory of Constraints, as Team 2 is the bottleneck affecting overall production efficiency. The Theory of Constraints focuses on identifying and managing the most critical limitation in a system. (See LO 3.3)



The operations department of ABC Ltd has recently launched a new product. The product is manufactured within a large factory and then sent to retailers for sale. The department has a system in place which details the components required for the product and the quantities required to fulfil customer demand. The system works online and links to other areas of the business including HR and finance.

So far, several large orders have been placed for the product from different retailers. The Chief Operations Officer (COO) has decided to programme the completion of the orders based on when the orders were placed. The benefit of this strategy is that it will give each customer a similar lead time. Thus far no buffer stock has been created as products are only created when orders are received.

Three teams are required to make the product and the product flows from team one to team two to team three, each team adding a component to the product. Unfortunately, team two are short staffed and are completing their work at a slower rate than the other two teams. This is a huge consideration for the COO as it will impact upon the capacity of the organisation.

The retailers have all signed contracts with ABC Ltd and the COO is extremely happy that they are long term contracts. Contract 1 is with retailer X and the price is set for three years. Contract 2 is with retailer Y and is a five year contract where the price will be reviewed annually in line with CPI. Contract 3 has a variable pricing mechanism based on the volume of products ordered.

What capacity strategy is being used?

  1. Demand-led
  2. Demand-lag
  3. Capacity-led
  4. Capacity-lag

Answer(s): A

Explanation:

The company follows a demand-led strategy since production capacity is adjusted based on actual customer orders. No stock is produced without confirmed demand. (See LO 2.2)



The operations department of ABC Ltd has recently launched a new product. The product is manufactured within a large factory and then sent to retailers for sale. The department has a system in place which details the components required for the product and the quantities required to fulfil customer demand. The system works online and links to other areas of the business including HR and finance.

So far, several large orders have been placed for the product from different retailers. The Chief Operations Officer (COO) has decided to programme the completion of the orders based on when the orders were placed. The benefit of this strategy is that it will give each customer a similar lead time. Thus far no buffer stock has been created as products are only created when orders are received.

Three teams are required to make the product and the product flows from team one to team two to team three, each team adding a component to the product. Unfortunately, team two are short staffed and are completing their work at a slower rate than the other two teams. This is a huge consideration for the COO as it will impact upon the capacity of the organisation.

The retailers have all signed contracts with ABC Ltd and the COO is extremely happy that they are long term contracts. Contract 1 is with retailer X and the price is set for three years. Contract 2 is with retailer Y and is a five year contract where the price will be reviewed annually in line with CPI. Contract 3 has a variable pricing mechanism based on the volume of products ordered.

What pricing mechanism is being used with supplier Y?

  1. Gain share
  2. Fixed price
  3. Variable price
  4. Indexation

Answer(s): D

Explanation:

Indexation is the correct pricing mechanism because the price is adjusted based on CPI (Consumer Price Index), which is a form of indexed pricing. This ensures that prices fluctuate in response to inflation or other economic indicators. (See LO 3.3)



Viewing page 5 of 18
Viewing questions 21 - 25 out of 84 questions