Implementing and Operating Cisco Data Center Core Technologies (DCCOR) Questions 181–185 (page: 38)

Updated On: 10-Feb-2026

A customer data center is configured for distribution of user roles, call home, and NTP. The data center was split into two geographically separate locations called
DC1 and DC2. The requirement is for the user role configurations to be distributed in DC1 and for NTP and call home features to be constrained to DC2. Which two configuration sets must be used to meet these requirements? (Choose two.)






Answer(s): B,D


Reference:

https://www.cisco.com/en/US/docs/storage/san_switches/mds9000/sw/rel_3_x/configuration/guides/cli_3_4_x/cfs.html#wp1306478



Refer to the exhibit. An engineer must distribute all the host ports to use all eight configured FEX uplinks. The solution must minimize disruption if an uplink fails.
Which action accomplishes this objective?

  1. Set the pinning max-links value to 8
  2. Configure the eight uplinks in a port channel
  3. Change the supported FEX type
  4. Statically assign each host interface to a fabric uplink

Answer(s): B

Explanation:

A fabric interface that fails in the port channel does not trigger a change to the host interfaces. Traffic is automatically redistributed across the remaining links in the port channel fabric interface. If all links in the fabric port channel go down, all host interfaces on the FEX are set to the down state.


Reference:

https://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus2000/sw/configuration/guide/ b_Cisco_Nexus_2000_Series_Fabric_Extender_Software_Configuration_Guide_Release_4_2/ b_Cisco_Nexus_2000_Series_Fabric_Extender_Software_Configuration_Guide_Release_4_2_chapter_011.html



An engineer must start a software upgrade on a Cisco Nexus 5000 Series Switch during a zone merge. What is the result of this action?

  1. The upgrade stops
  2. The zone merge pauses until the upgrade completes
  3. The zone merge stops
  4. The zone merge executes and then the upgrade completes

Answer(s): A


Reference:

https://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus5000/sw/upgrade/503_N1_1/n5000_upgrade_downgrade_503_n1_1.html



A network engineer needs to upgrade the EPLDs of the fabric modules for a Cisco MDS director-class switch. In which order are components reloaded during the process?

  1. one fabric module at the time
  2. all fabric modules followed by the entire switching platform
  3. all fabric modules in parallel
  4. one module and one supervisor at the time

Answer(s): D

Explanation:

To update all EPLDs sequentially with a single command, use the install all epld command with the module all fan-module all xbar all options. After each module is upgraded, it is power cycled to load the EPLD update.


Reference:

https://www.cisco.com/c/en/us/td/docs/switches/datacenter/mds9000/sw/8_x/release_notes/epld/epld_rn_8_4_1a.html#pgfId-321469



What is a characteristic of EPLD updates on Cisco MDS 9000 Series Switches?

  1. EPLD bundles are released separately from a Cisco MDS NX-OS release
  2. EPLD packages update hardware functionality on a device
  3. EPLD updates are nondisruptive to traffic flow
  4. EPLD updates are installed only via the Cisco DCNM GUI

Answer(s): B


Reference:

https://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus9000/sw/92x/epld-rn/nxos_n9K_epldRN_924.html