The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes. Which of the following best describes what the PM should work on FIRST?

  1. Project charter
  2. Project schedule
  3. Meeting agenda
  4. Responsibility assignment matrix
  5. Risk register

Answer(s): B



Which of the following charts is a graphical representation of the causes of a specific event?

  1. Histogram
  2. Scatter
  3. Fishbone
  4. Gantt

Answer(s): C

Explanation:

A fishbone diagram is a cause-and-effect diagram that shows the relationship between the effects of problems and their causes. This diagram depicts every potential cause of a problem and the effect that each proposed solution will have on the problem.



While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:

  1. quality plan.
  2. project management plan.
  3. risk register.
  4. process diagram.

Answer(s): A



A project team on a four-year project has a shortage of workspace within an office. Which of the following is the MOST viable solution for the project team while ensuring work hours are not wasted?

  1. Secure a new facility, permit remote work, and reduce staff.
  2. Reduce staff, implement BYOD, and permit remote work.
  3. Implement BYOD, secure a new facility, and utilize shared workspaces.
  4. Permit remote work, utilize shared workspaces, and implement BYO

Answer(s): D



A project is in the initiation phase. Which of the following tasks will take place during this phase?

  1. Develop a WBS.
  2. Define the project requirements.
  3. Create a project charter.
  4. Acquire the project resources.

Answer(s): C