A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early.


Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).

  1. Cost
  2. Predecessors
  3. Lag
  4. Durations
  5. Resource loading
  6. Subtasks
  7. Float

Answer(s): A,E



A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?

  1. Wait until the change requests are approved by the CCB.
  2. Approve the changes because the additional functionality is required to complete the process.
  3. Speak with the project sponsor and provide a detailed analysis of the changes and impacts to the project budget.
  4. Schedule the changes as part of the second phase of the project when additional funding will be available and work can be completed.

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 292



The chairperson of the board is visiting from another country and wishes to meet the project team members. The next project team meeting will be held next week, but the chairperson is leaving before the meeting. Which of the following actions should the project manager take?

  1. Schedule a conference call for the team meeting and invite the chairperson.
  2. Arrange an impromptu team meeting with the chairperson.
  3. Email the chairperson the meeting minutes from the scheduled meeting
  4. Invite the chairperson to the next project team meeting

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 259



Which of the following are characteristics of a project? (Choose two.)

  1. A project is a temporary endeavor.
  2. A project provides a unique product, service, or result.
  3. A project is an ongoing endeavor.
  4. A project involves scheduled maintenance.
  5. A project includes life-cycle cost management.

Answer(s): A,B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 71



Viewing page 28 of 182
Viewing questions 109 - 112 out of 1001 questions



Post your Comments and Discuss CompTIA PK0-004 exam prep with other Community members:

PK0-004 Exam Discussions & Posts