CompTIA PK0-004 Exam Questions
CompTIA Project+ (Page 28 )

Updated On: 17-Feb-2026

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:

-Coordinate project schedule
-Manage to the triple constraint
-Provide performance feedback to team members’ managers

Which of the following types of organizational structures did the new project manager MOST likely join?

  1. Balanced matrix
  2. Strong matrix
  3. Functional
  4. Projectized

Answer(s): D



Which of the following shows projected project expenditures?

  1. Work breakdown structure
  2. Cash flow schedule
  3. Cash burn rate
  4. Budget milestone

Answer(s): A



A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Choose two.)

  1. Using the WBS will help prevent work from slipping or being forgotten.
  2. TheWBS will be required on very large projects.
  3. TheWBS will be required if the project manager has the time available to complete it.
  4. TheWBS will aid in determining which resources are required for the project.
  5. The WBS is the best way to determine risks of the project.

Answer(s): A,D



A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?

  1. Issue log
  2. Action items
  3. Dashboard information
  4. Communication plan

Answer(s): A



Which of the following elements should be included on a responsibility assignment matrix?

  1. Responsible, accountable, consulted, informed
  2. Resource, accountable, signoff, input
  3. Responsible, accurate, confidential, informed
  4. Resource, accountable, consulted, informed

Answer(s): A






Post your Comments and Discuss CompTIA PK0-004 exam dumps with other Community members: