A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?
- Wait until the change requests are approved by the CCB.
- Approve the changes because the additional functionality is required to complete the process.
- Speak with the project sponsor and provide a detailed analysis of the changes and impacts to the project budget.
- Schedule the changes as part of the second phase of the project when additional funding will be available and work can be completed.
Answer(s): A
Reference:
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 292
Show Answer Next Question