Free PK0-005 Exam Braindumps
CompTIA Project+ Questions 201–208 (page: 27)

Updated On: 29-May-2026

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

  1. Transfer
  2. Avoid
  3. Accept
  4. Mitigate

Answer(s): A

Explanation:

By purchasing an extended warranty, the project manager is transferring the financial risk associated with potential server failures to the warranty provider, thereby protecting the project from unforeseen costs.



One of the key steps in controlling changes to software is obtaining approval. Which of the following statements BEST describes the reason for this key objective?

  1. To send the appropriate customer notifications
  2. To avoid a negative impact on other software functionalities
  3. To ensure adequate resources are in place to implement the change
  4. To confirm that the software is a business priority

Answer(s): B

Explanation:

Obtaining approval ensures that changes are carefully considered and assessed for their potential impact on the overall system, helping to maintain software integrity and functionality.



A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

  1. Regression testing
  2. Smoke testing
  3. Stress testing
  4. Automation testing

Answer(s): A

Explanation:

Regression testing is conducted to ensure that new changes, such as migrating data to a single system, do not adversely affect existing functionalities and performance of the system. It validates that the system still behaves as expected after modifications.



Which of the following can a project manager infer from the following velocity chart?

  1. The project is on schedule.
  2. The project is ahead of schedule.
  3. The project is behind schedule.
  4. The project is at risk.

Answer(s): B

Explanation:

From the velocity chart, it is clear that the Actual Effort (blue line) falls below the Planned Timeline (orange line) starting around day 12. This indicates that the project is progressing faster than expected, as the team is completing features ahead of the planned timeline.
The correct inference is "The project is ahead of schedule." This is supported by the chart showing that the actual effort is consistently lower than the planned timeline after day 12, meaning the team is completing work faster than initially planned.



A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the BEST tool to track this data?

  1. Gantt chart
  2. Project organization chart
  3. Program Evaluation Review Technique chart
  4. Milestone chart

Answer(s): D

Explanation:

A milestone chart focuses on tracking key deliverables or significant stages in a project without diving into the detailed tasks. It's ideal for high-level updates because it highlights the completion of major objectives, which is what the project lead would likely report on.



A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

  1. Planning
  2. Initiating
  3. Controlling
  4. Executing

Answer(s): A

Explanation:

The task of outsourcing portions of a project and conducting procurement typically occurs in the Planning phase.
In this phase, the project manager develops procurement management plans, identifies which parts of the project will be outsourced, prepares procurement documents, and selects vendors. This phase involves planning how procurement will be managed and ensuring that all necessary resources, including external vendors, are arranged before moving forward with execution.



A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

  1. Meeting cadence
  2. Gap analysis
  3. Dashboard
  4. Adoption training

Answer(s): C

Explanation:

In this scenario, the project sponsor is having difficulty providing the latest project status information, which suggests a need for a tool or method that can quickly and clearly present project progress.
The best option to address this issue is a dashboard.
The dashboard provides a real-time visual representation of key project metrics, such as progress, milestones, risks, and issues. It allows the project sponsor to quickly review and present up-to-date information during the weekly executive call.
This would ensure the sponsor has a clear, concise, and regularly updated view of the project's status.



A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

  1. List both positively and negatively impacted stakeholders.
  2. Update the communication plan with the new findings.
  3. List the negatively impacted stakeholders only.
  4. List the positively impacted stakeholders only.

Answer(s): A

Explanation:

The project manager should ensure that all stakeholders, both positively and negatively impacted, are properly accounted for and managed during the project. This ensures a balanced approach to stakeholder engagement and communication.
The best action for the project manager is to list both positively and negatively impacted stakeholders.
By listing both, the project manager can tailor communications and strategies to address the concerns of negatively impacted stakeholders while also leveraging the support of positively impacted ones. This helps in managing expectations and minimizing resistance to the new product.



Viewing page 27 of 79
Viewing questions 209 - 216 out of 628 questions


Post your Comments and Discuss CompTIA PK0-005 exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!