Which of the following offers administrators more direct control over operating systems?

  1. Infrastructure as a service
  2. Software as a service
  3. Functions as a service
  4. Platform as a service

Answer(s): A



Which of the following items must be protected as PII? (Choose two.)

  1. Job title
  2. Home address
  3. Work phone number
  4. Time zone
  5. Date of birth
  6. Blood type

Answer(s): B,E



A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

  1. Creation of a social news forum
  2. Management directives to use the new system
  3. New user kickoff meeting
  4. Monthly feedback and training sessions

Answer(s): D



A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:



Based on the chart, which of the following is the current status of the project?

  1. Behind schedule and over budget
  2. Behind schedule and under budget
  3. Ahead of schedule and over budget
  4. Ahead of schedule and under budget

Answer(s): A



Which of the following criteria would favor using the agile methodology to manage an upcoming project?

  1. Strong projectized organization
  2. Medium risk
  3. Lack of resources
  4. Multiple undefined tasks

Answer(s): D



A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

Purpose



Scope of work



Location of work



Period of performance



Deliverables schedule



Applicable standards



Acceptance criteria



Special requirements



Payment schedule



Which of the following documents did the client provide to the project manager?

  1. RFP
  2. WBS
  3. SLA
  4. SOW

Answer(s): D



While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

  1. Perform a root cause analysis.
  2. Organize a stakeholder meeting.
  3. Escalate the issue to the CCB.
  4. Contact the PMO for assistance.

Answer(s): D



A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

  1. A project manager assigned the wrong resources.
  2. A project manager did not release the resources.
  3. A project manager did not remove the system access.
  4. A project manager did not provide the project sign-off.

Answer(s): B