A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?
Answer(s): B
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.Which of the following is the current status of the process?
Answer(s): C
After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?
Answer(s): A
Post your Comments and Discuss CompTIA PK0-005 exam prep with other Community members:
Rezkin Commented on June 19, 2025 Great for flashcards UNITED STATES
sammy Commented on June 16, 2025 This is 100% Legit UNITED STATES
samsam Commented on February 28, 2025 i hope this will help me pass Anonymous
Ramba Commented on February 18, 2025 is this valid? EUROPEAN UNION
Jack Commented on December 07, 2024 are these legit ? Anonymous
Joe Commented on March 26, 2024 it helped me pass Anonymous