A project manager was just assigned to a new project.
Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

  1. Review the detailed plan.
  2. Develop a preliminary scope.
  3. Develop a transition plan.
  4. Develop a project management plan.
  5. Review the resource pool.
  6. Review the project objectives.

Answer(s): E,F



A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan.
Which of the following should be considered in this evaluation? (Select TWO).

  1. Company vision
  2. Global environment
  3. Brand value
  4. Mission statement
  5. Portfolio budget
  6. Local legislation

Answer(s): A,D



Halfway through a project, the sponsor states that the project is taking too long to complete.
Which of the following should the project manager consult?

  1. Gantt chart
  2. Maintenance window schedule
  3. Functional requirements
  4. Test results

Answer(s): A



A visual that displays team progress was created for stand-up meetings.
Which of the following BEST describes what is being represented on the visual?

  1. Decision board
  2. Whiteboard
  3. Task board
  4. Dashboard

Answer(s): C



A project manager is assigned to a multinational project with team members from different continents.
Which of the following is the MOST important aspect for the project manager to consider?

  1. Resource allocation
  2. Communication security
  3. Technological factors
  4. Cultural differences

Answer(s): D