PRINCE2 Foundation Exam (PR2F) Questions 76–80 (page: 17)

Updated On: 10-Feb-2026

Which describes the 'Implement' step within the recommended risk management procedure?

  1. Project Support will allocate the risk budget to fund the selected risk responses
  2. The risk owner will decide the best response to control the risk
  3. The risk owner and the risk actionee will carry out activities to control and deal with the risk
  4. The Project Manager will formulate the Risk Management Strategy

Answer(s): C



Which regular report provides the Project Board with a summary of stage status?

  1. Communication Management Strategy
  2. Project Brief
  3. Highlight Report
  4. Checkpoint Report

Answer(s): C



Which statement describes the Implement' step within the recommended risk management procedure?

  1. Take planned action to respond to a risk
  2. Implement the responsibilities for risks defined in the Risk Management Strategy
  3. Assess the proximity of a risk
  4. Identify the level of risks that can be tolerated by the project

Answer(s): A



Upon what environment is PRINCE2 based?

  1. Operational
  2. Configuration
  3. Programme
  4. Customer/supplier

Answer(s): D



What process is used by the Project Board to respond to an Exception Report?

  1. Controlling a Stage
  2. Managing a Stage Boundary
  3. Managing Product Delivery
  4. Directing a Project

Answer(s): D



Viewing page 17 of 50
Viewing questions 81 - 85 out of 296 questions