When are tolerances for a Work Package agreed?

  1. When accepting a Work Package
  2. As work on each product within the Work Package begins
  3. Once ail products have been developed and approved
  4. When the Stage Plan is authorized by the Project Board

Answer(s): A



Which risk response type is appropriate to respond to an opportunity?

  1. Accept
  2. Fallback
  3. Exploit
  4. Transfer

Answer(s): C



Which is an objective of the Managing Product Delivery process?

  1. Sign-off completed Work Packages
  2. Ensure the Business Case is kept under review
  3. Report progress to the Project Board
  4. Ensure that work on products is authorized and agreed with the team

Answer(s): D



Which product is NOT created in the Managing a Stage Boundary process?

  1. Benefits Review Plan
  2. End Stage Report
  3. Lessons Report
  4. Exception Plan

Answer(s): A



Which is NOT an objective of the Controlling a Stage process?

  1. Implement actions to control the impact of risks that occur during the stage
  2. Review the Business Case at regular intervals to assess the impact of changes that occur during the stage
  3. Update the Business Case with any changes agreed with the Project Board
  4. Coordinate the delivery of products as agreed in the Stage Plan

Answer(s): C