If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

  1. Checkpoint Report
  2. Highlight Report
  3. Issue Report
  4. Product Status Account

Answer(s): C



Which is an objective of the quality review technique?

  1. To baseline a product
  2. To provide a common understanding of what products a project will create
  3. To define the quality methods required within a project
  4. To determine the quality responsibilities of a project team

Answer(s): A



Which is NOT a type of issue?

  1. A problem/concern
  2. A constraint
  3. An off-specification
  4. A request for change

Answer(s): B



Which role is responsible for the management of a risk assigned to it?

  1. Project Support
  2. Risk owner
  3. Risk actionee
  4. Project Assurance

Answer(s): B



What is the definition of a project outcome?

  1. A measurable improvement that is perceived as an advantage by one or more stakeholders
  2. The reason for the project
  3. The result of the change derived from using the project's outputs
  4. The project's specialist products.

Answer(s): C