An input of the Control Schedule process is the:

  1. resource calendar.
  2. activity list.
  3. risk management plan.
  4. organizational process assets.

Answer(s): D



The Verify Scope process is primarily concerned with:

  1. formalizing acceptance of the completed project deliverables.
  2. accuracy of the work deliverables.
  3. formalizing approval of the scope statement.
  4. accuracy of the work breakdown structure (WBS).

Answer(s): A



What is the total float of the critical path?

  1. Can be any number
  2. Zero or positive
  3. Zero or negative
  4. Depends on the calendar

Answer(s): C



Portfolio Management is management of:

  1. a project by dividing the project into more manageable sub-projects.
  2. a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.
  3. all projects undertaken by a company.
  4. a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Answer(s): D



Which action should a project manager take to ensure that the project management plan is effective and current?

  1. Conduct periodic project performance reviews.
  2. Identify quality project standards.
  3. Follow ISO 9000 quality standards.
  4. Complete the quality control checklist.

Answer(s): A