As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?

  1. BAC
  2. EAC
  3. ETC
  4. WBS

Answer(s): B



How is scheduled variance calculated using the earned value technique?

  1. EV less AC
  2. AC less PV
  3. EV less PV
  4. AC less EV

Answer(s): C



The project management processes presented in the PMBOK Guide should:

  1. Always be applied uniformly
  2. Be selected as appropriate by the sponsor
  3. Be selected as appropriate by the project team
  4. Be applied based on ISO guidelines.

Answer(s): C



Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

  1. Project sponsor and project manager
  2. Project sponsor and functional manager
  3. Project manager and project team
  4. Project team and functional manager

Answer(s): C

Explanation:

The project management processes are presented as discrete elements with well- defined interfaces. However, in practice they overlap and interact in ways that are not completely detailed here. Most experienced project management practitioners recognize there is more than one way to manage a project. The specifics for a project are defined as objectives that must be accomplished based on complexity, risk, size, time frame, project team's experience, access to resources, amount of historical information, the organization's project management maturity, and industry and application area. The required Process Groups and their constituent processes are guides to apply appropriate project management knowledge and skills during the project. In addition, the application of the project management processes to a project is iterative and many processes are repeated and revised during the project. The project manager and the project team are responsible for determining what processes from the Process Groups will be employed, by whom, and the degree of rigor that will be applied to the execution of those processes to achieve the desired project objective.



Page 80 of 164



Post your Comments and Discuss GAQM PPM-001 exam with other Community members:

Maruthi commented on November 26, 2024
Good collection of the questions covering all aspects
AUSTRALIA
upvote

Ganapathy commented on November 26, 2024
Cam wr study and pass this Microsoft AZ-900 exam in India
Anonymous
upvote

Maruthi commented on November 26, 2024
Going all good
AUSTRALIA
upvote

Geroge commented on November 26, 2024
Providing this service is much appreciated. This free exam dumps is helping me a lot.
Romania
upvote

Anne commented on November 26, 2024
Took the exam today and I passed. I think I only had one new question, all were from here including the PBQ's
SOUTH AFRICA
upvote

elhassan commented on November 26, 2024
many thanks
Anonymous
upvote

willy commented on November 26, 2024
this web site help me to prepare for my exams
UNITED STATES
upvote

willy commented on November 26, 2024
Much better than the other website. its very helpful
UNITED STATES
upvote

Sigsauer9111 commented on November 26, 2024
I am looking to write the Ms-900, Just want to find out how accurate this exam dump and answers are in relation to the real exam?
Anonymous
upvote

Bright Edet commented on November 26, 2024
Valid dumps
Anonymous
upvote

jijo commented on November 26, 2024
its helpful
INDIA
upvote

sat commented on November 25, 2024
good content
Anonymous
upvote

Sameer Arshad commented on November 25, 2024
Excellent very useful
UNITED KINGDOM
upvote

Jeff commented on November 25, 2024
Wrote the exam and completed it in 15 minutes and pass with flying colours. One question was on what happens to a list when a new field is added to a table.
CANADA
upvote

mirnat Lime commented on November 25, 2024
I passed my exam using this Website. The Best and most accurate exam questions and answers are provided.
Anonymous
upvote

Umang Dhawan commented on November 25, 2024
Useful study material
Anonymous
upvote

precious Sithole commented on November 25, 2024
good quality knowledge
Anonymous
upvote

Sheetal commented on November 24, 2024
Just going through the questions for my understanding of Power Bi
Anonymous
upvote

Ben commented on November 24, 2024
good questions
FRANCE
upvote

Ozzie commented on November 24, 2024
great content
Anonymous
upvote

HAMID YAQUB commented on November 24, 2024
Great knowledge dump
UNITED KINGDOM
upvote

MG commented on November 24, 2024
I love it .Thanks
Anonymous
upvote

MG commented on November 24, 2024
It saved me for my exam preparationg .
Anonymous
upvote

Dev commented on November 24, 2024
Appreciate it very much
Anonymous
upvote

Crypt TH commented on November 24, 2024
its greate resource to prepre for the exam
JORDAN
upvote

Humtet commented on November 23, 2024
Very helpful and informative
CANADA
upvote

Oga commented on November 23, 2024
Graet very helpful
CANADA
upvote

kspp commented on November 23, 2024
Good Material
UNITED STATES
upvote

Saurabh commented on November 23, 2024
These are good dumps
UNITED STATES
upvote

cron commented on November 23, 2024
care to share those who bought this exam guide? more power
Anonymous
upvote

Lakshminarsimhan.R commented on November 23, 2024
The questions and answers are good in this portal, kindly please add comments as well for answers, so that it will be very hepful.
Anonymous
upvote

Naredn commented on November 22, 2024
Best practices at one place
Anonymous
upvote

max commented on November 22, 2024
thanks, i appreciate it
CANADA
upvote

Fefe commented on November 22, 2024
Great so far
Anonymous
upvote