Which of the following are inputs to Activity Definition?

  1. Project Scope Statement and Work Breakdown Structure
  2. Activity list and Arrow Diagram
  3. Change Requests Lists and Organizational Process Assets
  4. Project Management Plan and Resource Availability

Answer(s): A

Explanation:

Activity definition refers to the process of parsing a project into a number of individual tasks which must be completed before the deliverables can be considered completed. Activity definitions rely on a number of specific input processes. These include enterprise environmental factors, organizational process assets, the project scope statement, the work breakdown structure, the WBS dictionary, the project management plan (which consists of the project scope management plan and the schedule management plan). Through use of these inputs, the activities that will need to ultimately be completed in order to compete all of the project objectives can be readily defined, and the activity definition can be further accomplished through the utilization of a number of tools and techniques including decomposition, templates, rolling wave planning, expert judgment, and planning components. The four ultimate outputs of the activity definition process are the activity list, the resulting activity attributes, all requested changes, and any milestones. This term is defined in the 3rd edition of the PMBOK but not in the 4th.



Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?

  1. Schedule Control
  2. Activity Definition
  3. Schedule Development
  4. Activity Resource Estimating

Answer(s): D

Explanation:

Activity Resource Estimate Assumptions and Breakdown StructuresIn the Estimate Activity Resources process, the key output is activity resource requirements. These requirements describe the types and quantities of resources needed for each project activity.Once you know what resources you need, you can begin to estimate the time each activity will take to complete. In this way, the activity resource requirements list generated by the Estimate Activity Resources process become inputs for the Estimate Activity Durations process.
Activity resource requirements listThe activity resource requirements list identifies, for tracking purposes, the activity's code in the work breakdown structure, as well as its name. Vital to generating the project schedule, it details the resources that you've estimated you need to complete the activity, and addresses.
Resource description ­ The Resource description column lists each type of resource that is required for the activity. This includes human resources, materials, and facilities. Number required ­ The Number required column identifies the quantity required of each resource. This value can be specified in any measurement unit, such as hours, days, or physical number of units required.
Resource assumptions ­ Resource assumptions are important factors to consider when devising the project schedule. Any relevant assumptions about the resource can be included, for example resource availability, skills, or quality. Resource availability ­ The Resource availability column specifies when each resource can be used. This is vital information for putting together the project schedule. Resource dependencies ­ The Resource dependencies column identifies factors that may affect the availability of resources. It's important to identify dependencies when devising the project schedule because any change in an activity that has a dependency can affect the project timeline.The final row of the activity resource requirements list identifies the total resources needed for the activity. The resource totals are important in project scheduling as a base from which to calculate the duration of the activity. Resource Assumptions - It's important to record resource assumptions, as they can help during different stages of a project. Select each project stage to find out how resource assumptions can help.
Monitoring ­ Recorded assumptions can affect performance monitoring. For example, if a particular task seems to be taking too long, looking at the assumptions can help you identify the problem.
Controlling ­ Recorded assumptions can also help you control performance. Having used the assumptions to identify a problem, you can now make performance adjustments so that the project can run more efficiently.
Closing ­ Recorded assumptions can provide insights during post-project assessments at the closing stage. For example, if you had made incorrect assumptions about staff capabilities, looking at the assumptions helps you understand what went wrong. This can then be recorded in the lessons learned file for the project.Failure to record assumptions can also have an impact during the Monitor and Control Project Work process. Resource breakdown structuresAlong with the activity resource requirements list, there's one more main output of the Estimate Activity Resources process ­ the resource breakdown structure.The resource breakdown structure provides a hierarchical diagram of the resources required for a project. This structure is visually simple, showing resource information at a glance breaks resources into categories and resource types helps you to organize a project schedule and report on resource utilization information. Although they look similar, a resource breakdown structure is not the same as a work breakdown structure.
A work breakdown structure, or WBS, decomposes a project into manageable units of work. Elements in a WBS include project phases, tasks, sub-tasks, and work packages.
These represent all the activities in a project.
Project document updatesThe Estimate Activity Resources process concludes with project document updates ­ the final output of the process. Initially, various project documents are used as inputs for the process. Now that resource estimation is complete, new information may have come to light. For this reason, you may need to update documents so they reflect the latest project information.
In the process of estimating resource requirements and creating the resource breakdown structure, it's often necessary to add or delete schedule activities that appear in the activity list.The activity changes have a subsequent effect on activity attributes and resource calendars. Because project activities have changed, you need to document those changes by updating the descriptions of activities and the availability of relevant resources. The first output of the Estimate Activity Resources process is an activity resource requirements list. It's important to record any assumptions you've made about resources in this list, for use in monitoring and controlling project work, and in post-project assessments. A second output of the process is the resource breakdown structure. This is a hierarchical diagram that shows the resources required for the project in a visually simple way. It groups resources by category, and can be used for organizing and reporting on resources. The final output of the process is updates to relevant project documents, such as the activity list, activity attributes, and resource calendars.



Project scope statement and resource calendars are inputs to what Project Time Management process?

  1. Activity Sequencing
  2. Activity Resource Estimating
  3. Schedule Development
  4. Schedule Control

Answer(s): C



Which of the following tools or techniques is used for Estimate Activity Duration?

  1. Critical path
  2. Rolling Wave
  3. PDM
  4. Parametric

Answer(s): D



Page 85 of 164



Post your Comments and Discuss GAQM PPM-001 exam with other Community members:

Quentin commented on November 14, 2024
I noticed that some comments were related to answers not being 100% correct. But for me as long as questions are real and same as the actual exam I was okay.
Mexico
upvote

kagelelo commented on November 14, 2024
how do you pass the ged science test
Anonymous
upvote

Chris Nalla commented on November 14, 2024
Very insightful piece.
Anonymous
upvote

baba commented on November 14, 2024
want to learn
Anonymous
upvote

Anand commented on November 14, 2024
Not bad at all. It covers all the exam topics and it provides some insight to the types of questions that you are going to see in real exam.
INDIA
upvote

Godlover commented on November 14, 2024
Very up to date. I passed my exams. I studied very well though. But the past questions was exceedingly helpful too. Just practice the questions as much as you can. As for me I practiced all, and repracticed about 350 questions again before the exams day.
Anonymous
upvote

LasNumber commented on November 14, 2024
This Are Very Useful Q's and A's. on exam some Questions wont come as they are but mostly will come as the are. Study to Know
Anonymous
upvote

Yeshwanth commented on November 14, 2024
Nice Questions and helpful for exam preparation.
Anonymous
upvote

Jenil Gandhi commented on November 14, 2024
Hi everyone could sone share the certification voucher for PD2.
INDIA
upvote

Nicole commented on November 13, 2024
I am working towards my exam. Finding these prep to be very useful
CANADA
upvote

Nicole commented on November 13, 2024
Very helpful
CANADA
upvote

Bianca commented on November 13, 2024
Consistent questions
Anonymous
upvote

Larry commented on November 13, 2024
Good content
Anonymous
upvote

Dipu commented on November 13, 2024
Great Source , i feel really good questions
Anonymous
upvote

Dipu commented on November 13, 2024
Nice questions
Anonymous
upvote

Nathaniel Okeke commented on November 13, 2024
nice way to practice for the exam
Anonymous
upvote

Ashwini commented on November 13, 2024
I would appreciate for resources you can provide
INDIA
upvote

Ganiyu Ogunlana commented on November 13, 2024
Great Insight into the exams
Anonymous
upvote

Vuyo commented on November 13, 2024
Very Helpful
Anonymous
upvote

Suleman khan commented on November 13, 2024
Huawei is my favourite I'm enjoying these questions
PAKISTAN
upvote

Pandiyan Venkatraman commented on November 13, 2024
good question
Anonymous
upvote

Eb'Oney commented on November 12, 2024
I think the answer here should be B. Split the Logged column by using at as the delimiter
UNITED STATES
upvote

Hadiza commented on November 12, 2024
useful for exam preparation
Anonymous
upvote

Hadiza commented on November 12, 2024
inspiring and educative
Anonymous
upvote

Hadiza commented on November 12, 2024
Highly resourceful
Anonymous
upvote

Naomie commented on November 12, 2024
Good material very helpful.
Anonymous
upvote

dodol commented on November 12, 2024
ok real exam
Anonymous
upvote

PA commented on November 11, 2024
This questions are valid in Canada. I passed the exam.
CANADA
upvote

JP commented on November 11, 2024
Très intéréssant pour valider son apprentissage
SWITZERLAND
upvote

JP commented on November 11, 2024
Good for exam preparation
SWITZERLAND
upvote

K.U commented on November 11, 2024
@Dane, Yes, questions are very similar to content of real exam. I managed to pass the test.
Anonymous
upvote

siva N commented on November 11, 2024
this absolutely make the test easy!!!
INDIA
upvote

Isadora Guimarães commented on November 10, 2024
Very good to study
UNITED STATES
upvote

Noah commented on November 10, 2024
Does this dump include the lab solution as well?
Anonymous
upvote