The inputs of the Performance Reporting process include all of the following except for which one?
Answer(s): A
Performance reviews are not an input of the Performance Reporting process. The remaining inputs of this process are quality control measurements, project management plan, approved change requests, and deliverables.
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You know, but have not yet informed your company, that you are going to go to work for the competitor, which happens to be bidding for this same opportunity.What is the most appropriate response?
Answer(s): C
The most appropriate response is to decline to participate because of a conflict of interest.
The most effective team motivator is:
Answer(s): D
Complete final contract performance reporting and verify product is done in _______ .
Answer(s): B
Complete final contract performance reporting and verify product is done in Close Procurements.
Continually measuring and monitoring the actual cost versus the budget is done to __________.