You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of scope definition. Which of the following could happen if you don't correct this?
Answer(s): A
You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them with training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following statements is true?
When people work in unfamiliar environments, culture shock can occur. Training and researching information about the country you'll be working in can help counteract this.
Which of the following is not true for a Responsibility Assignment Matrix (RAM):
Answer(s): D
The Responsibility Assignment Matrix (RAM) details the different tasks for the people listed in the matrix chart.
The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.
Answer(s): C
You are the project manager of a project .You have just completed the CollectRequirements and Define Scope. What should you do next?
Answer(s): B
Create the WBS is the process that follows Collect Requirements and Define Scope.