GAQM PPM-001 Exam Questions
Professional in Project Management (PPM) (Page 25 )

Updated On: 17-Feb-2026

Formal written correspondence is mandated in which of the following situations:

  1. Client requests additional work not covered under contract
  2. None of the other alternatives apply
  3. Both 1) Client requests additional work not covered under contract, and 2) Project manager calls a meeting.
  4. Project manager calls a meeting
  5. Product undergoes casual in-house testing

Answer(s): A



Smoothing out resource requirements from period to period is called resource _____.

  1. None of the other alternatives apply.
  2. Leveling.
  3. Quantification
  4. Partitioning
  5. Allocation.

Answer(s): B



You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away.
Which of the following statements is true?

  1. This project ended due to integration because it was completed and accepted.
  2. This project ended due to extinction because it was completed and accepted.
  3. This project ended due to integration because it was completed and accepted and the project manager moved on to a new project.
  4. This project ended due to addition because it was completed and accepted and archived into the company's catalog of available films.

Answer(s): B

Explanation:

Extinction is the best type of project end because it means the project was completed successfully and accepted by the sponsor or customer.



Which is a valid response to negative risks?

  1. mitigation
  2. Enhance
  3. Exploit
  4. Share

Answer(s): A

Explanation:

Risk mitigation is a response to negative risks and not positive risks. Positive risks may be responded by - "Exploit", "Enhance", "Share", "Accept".



Project leadership requires that the project manager pay attention simultaneously to the:

  1. Time, cost and performance deliverables
  2. Tasks to be performed and needs of the team
  3. Quantity and quality of the work to be performed
  4. All of the other alternatives apply
  5. Efficiency and effectiveness of the team

Answer(s): D






Post your Comments and Discuss GAQM PPM-001 exam dumps with other Community members:

Join the PPM-001 Discussion