Free PPM-001 Exam Braindumps
Professional in Project Management (PPM) Questions 181–185 (page: 38)

Updated On: 10-Feb-2026

All the techniques described below can be used to keep a meeting focused except:

  1. Rephrase unclear ideas presented by group members
  2. Encourage pursuit of interesting new ideas
  3. Summarize discussion periodically
  4. Recall agenda items/purpose of meeting
  5. All are acceptable techniques

Answer(s): B



Resource leveling _____.

  1. Attempts to reduce resource requirements within a constraint on project duration
  2. Smoothes out resource requirements by rescheduling activities within their float time.
  3. Allocates resources to activities to find shortest schedule within fixed resource limits.
  4. Smooths out resource requirements by substituting activities with unassigned resources.
  5. 1) Smoothes out resource requirements by rescheduling activities within their float time, or 2) Attempts to reduce resource requirements within a constraint on project duration

Answer(s): E



The highest degrees of project risk and uncertainty are associated with the following phase of the project:

  1. Both 1) conceptual, and 2)post project evaluation
  2. cut-over
  3. conceptual
  4. execution
  5. post project evaluation

Answer(s): C



You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements.
Which of the following is not a valid option?

  1. You document the poor performance in written form and send the correspondence to the subcontractor.
  2. You terminate the contract for poor performance and submit a change request through Contract Administration.
  3. You agree to meet with the subcontractor to see whether a satisfactory solution can be reached.
  4. You submit a change request through Contract Administration demanding that the subcontractor comply with the terms of the contract.

Answer(s): D

Explanation:

The contract change control system describes the processes you'll use to make changes to the contract, not as a means of communication. The changes might include contract term changes, date changes, and termination of a contract.



Job descriptions are examples of ______communications.

  1. horizontal
  2. downward
  3. diagonal
  4. upward
  5. None of the other alternatives apply

Answer(s): E



Viewing page 38 of 131
Viewing questions 186 - 190 out of 650 questions


Post your Comments and Discuss GAQM PPM-001 exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!