Which performance measurement tells you what the projected total cost of the project will be at completion?
Answer(s): C
Estimate at completion (EAC) estimates the total cost of the project at completion based on the performance of the project to date.
Your project team consists of 12 people in the same building you're located in, 4 people from the West Coast office, 2 people from the Kansas City office, and 6 people from the London office. Your office works different hours than all the other offices. Additionally, not all of the resources in your building are available at the same times during the day. Three of the 12 team members work swing shift hours. You use tools like web conferencing and email to distribute information to the team. Which of the following is true?
Answer(s): D
Virtual teams are teams that don't necessarily work in the same location or have the same hours but all share the goals of the project and have a role on the project. The web conferencing and email references describe the information distribution methods tool and technique of the Information Distribution process.
You are a project manager for a documentary film company. In light of a recent regional tragedy, the company president wants to get a new documentary on the rescue efforts of the heroic rescue teams to air as soon as possible. She's looking to you to make this documentary the best that has ever been produced in the history of this company. She guarantees you free rein to use whatever resources you need to get this project done quickly. However, the best photographer in the company is currently working on another assignment. Which of the following is true?
Answer(s): B
The primary constraint is quality. If you made the assumption as stated in "Resources are the primary constraint. Even though the president has given you free rein on resource use, you assume she didn't mean those actively assigned to projects.", you assumed incorrectly. Clarify these assumptions with your stakeholders and project sponsors. This applies to "The schedule is the primary constraint. Even though the president has given you free rein on resource use, you assume she didn't mean those actively assigned to projects. The photographer won't be finished for another three weeks on his current assignment, so schedule adjustments will have to be made." as well.
Which may be employed to shorten a schedule without changing the scope of the task?
Surveys have shown that the primary skill needed to be a project manager is communication skill. The typical project manager spends approximately ______percent of his or her time communicating.