You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower's site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300, AC = 200, and EV = 250. What is the CPI of this project?
Answer(s): C
CPI is calculated as follows: EV ÷ AC. In this case, 250 ÷ 200 = 1.25.
A work breakdown structure is most useful for:
Answer(s): E
You are the project manager for a top-secret software project for an agency of the United States government. Your mission-should you choose to accept it-is to complete the project using internal resources. The reason is that finding contractors with top-secret clearances takes quite a bit of time, and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director's hot new project. Which of the following type of project ending is this?
Answer(s): D
Integration occurs when resources, equipment, or property are reassigned or redeployed back to the organization or to another project.
Define Activities is typically performed by which of the following:
Define Activities is typically performed by Project Team Members. identify the activities that need to be done to complete the project.
Which of the following is closest to Juran's definition of Quality:
Answer(s): B