Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?

  1. Analogous Estimating
  2. Expert Judgment
  3. Optimistic Estimates
  4. Reserve Analysis

Answer(s): D



Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

  1. Applying calendars
  2. Resource Leveling
  3. Resource Planning
  4. Resource Conflict Management

Answer(s): B



Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?

  1. Performance organizations
  2. Schedule baselines
  3. Performance measurements
  4. Change requests

Answer(s): C



Which technique is utilized in the Schedule Control process?

  1. Performance Measure
  2. Baseline Schedule
  3. Schedule Comparison
  4. Variance Analysis

Answer(s): D



Cost baseline is an output of which of the following processes?

  1. Cost Control
  2. Cost Budgeting
  3. Cost Estimating
  4. Cost Planning

Answer(s): B