Analogous Cost Estimating relies on which of the following techniques?

  1. Expert Judgment
  2. Project Management Software
  3. Vendor Bid Analysis
  4. Reserve Analysis

Answer(s): A



The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:
Actual cost = $50,000
Plan cost = $45,000
Earned value = $40,000
What is the cost performance index?

  1. 0.80
  2. 0.89
  3. 1.13
  4. 1.25

Answer(s): A



The PV is $1000, EV is $2000 and AC is $1500.
What is CPI?

  1. 1.33
  2. 2.00
  3. 0.75
  4. 0.5

Answer(s): A



At the end of the project, what will be the value of SV?

  1. Positive
  2. Zero
  3. Negative
  4. Greater than one

Answer(s): B



Which is one of the determining factors used to calculate CPI?

  1. EV
  2. SPI
  3. PV
  4. ETC

Answer(s): A