Free H12-425 Exam Braindumps (page: 8)

Page 8 of 61

When the air conditioning outdoor of Huawei air-cooled air conditioner is installed horizontally, it is required to be (___________________) mm from the wall or obstacle.

  1. 100
  2. 200
  3. 300
  4. 600

Answer(s): D



FusionModule1000 is an indoor prefabricated all in-one data center solution.

  1. TRUE
  2. FALSE

Answer(s): B

Explanation:

FusionModule1000A All-in-One Prefabricated Data Center is a green and reliable outdoor data center solution.



After the UPS5000-E system is installed, which of the following items need to be checked?

  1. if UPS and battery system mechanical installation is firm and stable
  2. if the cable layout considers other system wiring in the future
  3. if the ground connection is reliable
  4. The positive and negative terminals of the battery are wired correctly.

Answer(s): A,B,C,D



Backup time of battery depends on discharge current of battery.

  1. TRUE
  2. FALSE

Answer(s): A



Page 8 of 61



Post your Comments and Discuss Huawei H12-425 exam with other Community members:

Temesgen fentabil commented on June 13, 2024
It is good h12-425 exam related questions
Anonymous
upvote