After the UPS5000-E system is installed, which of the following items need to be checked?

  1. if UPS and battery system mechanical installation is firm and stable
  2. if the cable layout considers other system wiring in the future
  3. if the ground connection is reliable
  4. The positive and negative terminals of the battery are wired correctly.

Answer(s): A,B,C,D



Backup time of battery depends on discharge current of battery.

  1. TRUE
  2. FALSE

Answer(s): A



The higher the batteries discharge current is, the shorter the discharge time is.

  1. TRUE
  2. FALSE

Answer(s): A



If the rotation function of the teamwork is enabled, the active and the standby air conditioners can work alternatively to prolong their service life.

  1. TRUE
  2. FALSE

Answer(s): A



Which air supply modes requires reasonable raised floor height?

  1. Air supply mode using blast caps
  2. Under floor air supply mode.
  3. Air supply mode using wind pipe
  4. In-row horizontal air supply mode

Answer(s): B