What function of NETECO needs to be used ( ) if the customer wants to know the status of the equipment on and off the shelf and the capacity of the cabinet.

  1. Work Order Management
  2. Energy Efficiency Management
  3. Asset Management
  4. Capacity Management

Answer(s): C



UPS5000-E only needs to select ( ), it can easily realize 2N power supply system, and the operation is simple and convenient. .

  1. BSC cable
  2. Sync Controller
  3. BSC Control Board
  4. Parallel card

Answer(s): A



Using UPS5000-E (50kVA power module), the actual load is 160kW, the rack 1+1 redundancy, the single-machine backup power scheme is adopted, each rack has 3 groups of batteries, each group is 40, and the capacity of the main switch box is ( )

  1. 250A
  2. 320A
  3. 500A
  4. 630A

Answer(s): C



How many 12V batteries can the optional battery inspection instrument of UPS5000-A-400/500K support? ( )

  1. 12
  2. 24
  3. 32
    D .40.

Answer(s): B



The wrong description about the reliability of NetCol5000-C row-level air conditioner is: ().

  1. It adopts dual power supply, and the two power supply adopts automatic switching mode
  2. Large-scale data centers such as operators and large corporate headquarters are more popular with such air conditioners. .
  3. More application of SMEs Netcp15000-A air conditioner multi-fan air supply: online maintenance is possible.
  4. Cannot be used in scenarios without raised floor, because condensate drainage cannot be connected to the pipe

Answer(s): D