You are the business analyst for your organization and you're notifying the key stakeholders of a need to gather requirements for an endeavor. One of the stakeholders that you'll need to attend your requirements workshop is the project manager.
What role will the project manager have in this workshop?

  1. The project manager will facilitate the requirements workshop.
  2. The project manager will ensure that the needed resources are available.
  3. None, the project manager should not be involved until all of the requirements have been identified.
  4. The project manager will help elicit requirements from the stakeholders.

Answer(s): B

Explanation:

The role of the project manager in elicitation tasks is to ensure that the needed resources are available. Answer C is incorrect. The project manager will likely be involved in the requirements workshop.

Answer A is incorrect. The project manager won't facilitate the requirements workshop, the business analyst will.
Answer D is incorrect. The project manager may help elicit requirements from stakeholders, but this isn't the best choice for the Question.



You are a Business Analyst for your organization, and you're preparing to elicit requirements from stakeholders. You've gathered several inputs to help with the elicitation process.
Which input will you use to ensure that you understand the type of information that should be elicited from stakeholders?

  1. Roles and Responsibilities
  2. Stakeholder List
  3. Business Need
  4. Risk Assessment

Answer(s): C

Explanation:

The inputs required to prepare for elicitation are as follows:
Business Need. It guarantees that the type of information elicited from stakeholders is understood to the business analyst. This input is used at the time of eliciting business requirements. Solution Scope and Business Case. It guarantees that the type of information elicited from stakeholders is understood to the business analyst. This input is used at the time of eliciting stakeholder, transaction requirement, and solution.
Stakeholder List, Roles, and Responsibilities. It is required for the identification of stakeholders that are required to participate in elicitation activity.
Answer D is incorrect. Risk Assessment is a review of the risks in the project, and isn't an input to the elicitation business analyst tasks.



Nancy has asked you to trace a particular requirement for her.
What does 'to trace a requirement' mean?

  1. Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to components in the project's work breakdown structure.
  2. Tracing a requirement means to track a requirement from its first identification all the way to its completion to see what issues, risks, costs, quality, and defects have surrounded the requirement.
  3. Tracing a requirement means to look at a requirement and the others to which it is related. It links risk, cost, quality, and scope elements to stakeholder and solution requirements to other artifacts created by the team and to solution components.
  4. Tracing a requirement means to look at a requirement and the others to which it is related. It links business requirements to stakeholder and solution requirements to other artifacts created by the team and to solution components.

Answer(s): D

Explanation:

Tracing a requirement is the linkage of the requirements to all the parts of solution including its execution and creation.
Answer C is incorrect. This is not a valid definition of tracing a requirement. Requirement tracing does not consider risk, cost, quality, and other scope elements. Answer A is incorrect. This is not a valid definition of tracing a requirement. It does not examine its position in the project WBS.



Which elicitation activity is best described to ensure that the needed resources are organized and available for the elicitation?

  1. Confirming elicitation results
  2. Preparing for elicitation
  3. Planning for elicitation
  4. Managing stakeholder requirements

Answer(s): B

Explanation:

In order to conduct the elicitation process, the business analyst must work with the appropriate people, such as the project manager, to ensure that the needed resources are organized and available for the elicitation. Answer C is incorrect. Planning for elicitation is not a valid elicitation task.
Answer A is incorrect. Confirming elicitation results is the confirmation that the business analyst understands the requirements and that the stakeholder confirms the results of the elicitation. Answer D is incorrect. Managing stakeholder requirements is not a valid elicitation task.



Page 35 of 129



Post your Comments and Discuss IIBA CCBA exam with other Community members:

Mohammed Basheer commented on August 23, 2017
Wrote the exam today and I passed it easily. Valid dump!
UNITED STATES
upvote