Free CCBA Exam Braindumps (page: 4)

Page 4 of 129

Henry and Fred are working together on business analysis duties for the implementation of new software. Henry, the business analyst, tells Fred that they should take the current measurement of productivity, and then measure again after the solution has been implemented. This benchmarking approach will allow Henry and Fred to see the real effect of the solution on the business need.
What term is assigned to this measurement?

  1. Post implementation factor
  2. Yield
  3. Key performance indicators
  4. S-Curve

Answer(s): C

Explanation:

The measurements are known as key performance indicators. It's an approach for measuring how well the solution has affected the organization.
Answer D is incorrect. The S-curve describes the direction of elements over time, such as time and cost, in a typical business analysis activity or in a project. Answer B is incorrect. The yield is the output of the effort.

Answer A is incorrect. It is not a business analysis term so this choice is incorrect.



Kendra is the business analyst for her organization. She's working with the project manager and the project sponsor to discuss the current requirements. Kendra believes it's important for the project manager to first implement the requirements with the highest amount of risks. Is this a good idea?

  1. No, the project manager and team should actually implement the lowest risk requirements first.
  2. Yes, if the risky requirements cause the project to fail, the organization will not suffer much loss, as it hasn't invested much time or money on the project.
  3. No, the project manager and team should implement the requirements with the highest risks last.
  4. Yes, this allows the project manager to get the risky work done as soon as possible in the schedule.

Answer(s): B

Explanation:

It's often best to implement the most risky requirements first in the project. If the risky requirements cause the project to fail, the organization will not suffer much loss, as it hasn't invested much time or money on the project.
Answer A is incorrect. It's not the best idea to implement the lowest risk requirements first.

Answer C is incorrect. Implementing the highest risk requirements last could cause all of the prior work to be worthless if the risky requirements fail. Answer D is incorrect. This choice is tempting, but the best reason is the financial consideration of the risky event in the project.



A business analyst is studying the cost of the endeavor in relation to the projected income the endeavor will bring once the project is completed.
What financial valuation technique can the business analyst use to determine the breakeven point for the project?

  1. Payback period
  2. Average rate of return
  3. Cost-benefit analysis
  4. Discounted cash flow

Answer(s): A

Explanation:

Payback period quantifies the duration that the project will need to exist and generate revenue in order to pay back the original investment of the project. The payback period is also known as management horizon or the breakeven point.
Answer B is incorrect. Average rate of return describes the rate of return the project will create. Answer C is incorrect. Cost-benefits analysis describes the relation of costs to benefits in a project. Answer D is incorrect. Discounted cash flow describes the future value on the investment of the project.



When a business analyst completes the elicitation process, she will create four outputs.
Which one of the following is an output of the elicitation process?

  1. Requirements management plan
  2. Resource identification
  3. Stakeholder Concerns
  4. Solution scope

Answer(s): C

Explanation:

Following are the outputs of the elicitation process:
Stakeholder Concerns Elicitation Results Schedule Resources Supporting Materials



Page 4 of 129



Post your Comments and Discuss IIBA CCBA exam with other Community members:

Mohammed Basheer commented on August 23, 2017
Wrote the exam today and I passed it easily. Valid dump!
UNITED STATES
upvote