You are the business analyst for a large software development project. There are several issues that must be resolved by certain dates or the problem will prevent the project from advancing.
What technique can you use to track problems with the requirements?

  1. Issue tracking
  2. RTM
  3. Problem tracking
  4. Baselining

Answer(s): C

Explanation:

The technique you'll use is simply problem tracking. This technique allows the business analyst to manage any issues identified within requirements by stakeholders and to ensure that those issues are resolved.
Problem tracking allows the business analyst to manage any issues identified within requirements by stakeholders and to ensure that those issues are resolved. It provides an organized approach to tracking, management, and resolution of defects, issues, problems, and risks throughout business analysis activities. Management of issues is important so that they can be resolved in a timely manner to ensure success.
Answer D is incorrect. Baselining the requirements does not track problems but creates a standard set of requirements that deliverables may be compared against.

Answer A is incorrect. Issue tracking is not a valid business analysis term.

Answer B is incorrect. An RTM is a requirements trace matrix which tracks requirements through the solution, not issues.



Which one of the following statements is most true about changing requirements in a change-driven approach to business analysis and requirements management?

  1. Change-driven approaches must use a change control system with a change control board.
  2. Change-driven approaches only use a change control system for approved changes.
  3. Change-driven approaches don't use a formal change control process.
  4. Change-driven approaches are driven by change control processes.

Answer(s): C

Explanation:

Change-driven approaches typically do not use a formal change control process, as requirements are prioritized and selected for implementation at the beginning of each iteration and no changes to the requirements occur during the iteration process.
Answer A is incorrect. Change-driven approaches don't typically use a change control board.

Answer B is incorrect. This isn't a valid statement to describe the processes of change within a change-driven approach to requirements management.
Answer D is incorrect. This isn't a valid statement to describe the processes of change within a change-driven approach to requirements management.



Which element of the process of assessing the capability gaps is best described as gathering as much enterprise architecture information as is available about the current state of the organization and the areas affected by the business need?

  1. Current capability analysis
  2. Current organizational needs assessment
  3. Enterprise architecture assessment
  4. Snapshot baseline

Answer(s): A

Explanation:

Current capability analysis is an approach of assessing the organization's capability gaps. This process reviews the process and helps determine what capabilities exist now and how large the gap may be. Answer C is incorrect. This isn't a valid assessment type so this choice is not valid. A. See Explanation section for answer.

Answer(s): A

B is incorrect. This isn't a valid assessment type so this choice is not valid. Answer D is incorrect. This isn't a valid assessment type so this choice is not valid.



Beth is the business analyst for her organization and she wants to be certain that she and her team follow the correct procedures for enterprise analysis.
What document can provide the governances for enterprise analysis efforts?

  1. Organizational process assets
  2. Enterprise environmental factors
  3. Business analysis plans
  4. Project charter

Answer(s): C

Explanation:

Business analysis plans define the governance or rules and procedures that Beth should follow as the business analyst for her organization.
Answer A is incorrect. Organizational process assets are the rules and procedures for the implementation of documents, templates, and guidelines. Answer B is incorrect. Enterprise environmental factors are the regulations, policies, and procedures that are unique to an organization and industry. Answer D is incorrect. The project charter isn't the correct answer, as the charter authorizes the project, not business analysis activities.



Page 3 of 129



Post your Comments and Discuss IIBA CCBA exam with other Community members:

Mohammed Basheer commented on August 23, 2017
Wrote the exam today and I passed it easily. Valid dump!
UNITED STATES
upvote