In order to plan business analysis activities, you will need four inputs.
Which one of the following inputs is not valid for this task?

  1. Business analysis approach
  2. Stakeholder tolerance for risk
  3. Stakeholder list, roles, and responsibilities
  4. Business analysis performance assessment

Answer(s): B

Explanation:

Stakeholder tolerance for risk is not a valid input for planning business analysis activities. Answer A, D, and C are incorrect. Following are the inputs in Plan Business Analysis Activities: Business Analysis Approach
Business Analysis Performance Assessment Organizational Process Assets Stakeholder List, Roles, and Responsibilities



Wanda is the business analyst for her organization and she is currently working on the specify and model requirements process. One of the elements of this process is the documentation of the textual requirements. Wanda must describe the capabilities of the solution, any conditions that must exist for the requirements to operate, and what third component of the textual requirement?

  1. Any constraints that may prevent the solution from fulfilling the requirement
  2. Describe a situation or problem
  3. Write in the active voice
  4. Express only one requirement at a time

Answer(s): A

Explanation:

The third component of the textual requirements is that Wanda must also identify any constraints that will prevent the solution from fulfilling the requirement. Answer D is incorrect. To express only one requirements at a time is a guideline for the process, but not a component of the process.
Answer B is incorrect. To describe a situation or problem is a guideline for the modeling formats. Answer C is incorrect. Writing in the active voice is good guideline for the textual requirements, but it is not part of the text requirements.



As a candidate for CCBA, you should be able to recognize the activities associated with each knowledge are

  1. Which of the following are business analysis planning and monitoring activities? Each correct answer represents a complete solution.
  2. Job shadowing
  3. Planning how requirements will be approached, traced, and prioritized
  4. Identifying stakeholders
  5. Defining and determining business analysis processes

Answer(s): B,C,D

Explanation:

The most common business analysis planning and monitoring activities are. identifying stakeholders, defining roles and responsibilities of stakeholders in the business analysis effort, developing estimates for business analysis tasks, planning how the business analyst will communicate with stakeholders, planning how requirements will be approached, traced, and prioritized, determining the deliverables that the business analyst will produce, defining and determining business analysis processes, and determining the metrics that will be used for monitoring business analysis work. Answer A is incorrect. Job shadowing is an elicitation process that is a part of job observation. In this process, the observer is required to keep an eye on those workers whose work routine is down and who are unable to explain their work. The observer has to understand their work process for better assessment of the modifications of the work required. The following are the approaches for this technique:
Passive/Invisible. In this approach, the observer does not ask Questions from the user about his work while the user is working.
Active/Visible. In this approach, the observer does ask Questions from the user about his work even when the user is working.



Ralph is a business analyst for his organization and he's using the plan-driven approach for business analysis. Ralph has captured the requirements of the project, but what must happen before he can begin capturing and defining the requirements at a deeper level of detail?

  1. The initial requirements must be tested for time, cost, quality, and risk.
  2. The initial requirements must undergo a feasibility study.
  3. The initial requirements must be formally approved by the stakeholders.
  4. The initial requirements must pass through the Delphi Technique.

Answer(s): C

Explanation:

Before Ralph can begin defining the requirements at a deeper level, the initial requirements must be formally approved by the relevant stakeholders.
Answer B is incorrect. The initial requirements do not need to undergo a feasibility study at this time. Answer D is incorrect. The Delphi Technique is useful to gain consensus on requirements, but it's not a mandatory activity or needed (usually) with the initial requirements. Answer A is incorrect. The requirements don't need to be tested for time, cost, quality, and risk at this time.



You are the business analyst for your organization and you're creating a business analysis communications management plan. In your plan, you want to address the different locales and culture and the communication needs that may affect the business analysis approach.
Which one of the following elements should not be included in the cultural analysis of the plan?

  1. Relationship to task completion
  2. Relationship to authority
  3. Relationship to religion
  4. Relationship to time

Answer(s): C

Explanation:

Of course, the business analyst should not include the stakeholder's relation to religion. The business analyst should document the relationship to time, task completion, contracts, and authority. Answer D is incorrect. Relationship to time is a valid consideration for the cultural analysis of the communications management plan.
Answer A is incorrect. Relationship to task completion is a valid consideration for the cultural analysis of the communications management plan.
Answer B is incorrect. Relationship to authority is a valid consideration for the cultural analysis of the communications management plan.



Viewing page 52 of 104
Viewing questions 256 - 260 out of 638 questions