Certified Information Security Manager Questions 461–465 (page: 94)

Updated On: 10-Feb-2026

Which of the following BEST protects against web-based cross-domain attacks?

  1. Database hardening
  2. Application controls
  3. Network addressing scheme
  4. Encryption controls

Answer(s): B



Which of the following would be MOST effective in preventing malware from being launched through an email attachment?

  1. Up-to-date security policies
  2. Placing the e-mail server on a screened subnet
  3. Security awareness training
  4. A network intrusion detection system (NIDS)

Answer(s): C



Which of the following risks would BEST be assessed using quantitative risk assessment techniques?

  1. Customer data stolen
  2. An electrical power outage
  3. A web site defaced by hackers
  4. Loss of the software development team

Answer(s): B

Explanation:

The effect of the theft of customer data or web site defacement by hackers could lead to a permanent decline in customer confidence, which does not lend itself to measurement by quantitative techniques. Loss of a majority of the software development team could have similar unpredictable repercussions. However, the loss of electrical power for a short duration is more easily measurable and can be quantified into monetary amounts that can be assessed with quantitative techniques.



The impact of losing frame relay network connectivity for 18-24 hours should be calculated using the:

  1. hourly billing rate charged by the carrier.
  2. value of the data transmitted over the network.
  3. aggregate compensation of all affected business users.
  4. financial losses incurred by affected business units.

Answer(s): D

Explanation:

The bottom line on calculating the impact of a loss is what its cost will be to the organization. The other choices are all factors that contribute to the overall monetary impact.



Which of the following is the MOST usable deliverable of an information security risk analysis?

  1. Business impact analysis (BIA) report
  2. List of action items to mitigate risk
  3. Assignment of risks to process owners
  4. Quantification of organizational risk

Answer(s): B

Explanation:

Although all of these are important, the list of action items is used to reduce or transfer the current level of risk. The other options materially contribute to the way the actions are implemented.



Viewing page 94 of 345
Viewing questions 466 - 470 out of 1716 questions


Post your Comments and Discuss ISACA CISM exam prep with other Community members: