Which of the following is described by the definition given below? "It is the expected guaranteed value of taking a risk."

  1. Certainty equivalent value
  2. Risk premium
  3. Risk value guarantee
  4. Certain value assurance

Answer(s): A

Explanation:

The Certainty equivalent value is the expected guaranteed value of taking a risk. It is derived by the uncertainty of the situation and the potential value of the situation's outcome.

Incorrect Answers:
B: The risk premium is the difference between the larger expected value of the risk and the smaller certainty equivalent value.

C, D: These are not valid answers.



You are the project manager of GHT project. Your hardware vendor left you a voicemail saying that the delivery of the equipment you have ordered would not arrive on time. She wanted to give you a heads-up and asked that you return the call. Which of the following statements is TRUE?

  1. This is a residual risk.
  2. This is a trigger.
  3. This is a contingency plan.
  4. This is a secondary risk.

Answer(s): B

Explanation:

Triggers are warning signs of an upcoming risk event. Here delay in delivery signifies that there may be a risk event like delay in completion of project. Hence it is referred to as a trigger.

Incorrect Answers:
A: Residual risk is the risk that remains after applying controls. But here in this scenario, risk event has not occurred yet.

C: A contingency plan is a plan devised for a specific situation when things go wrong. Contingency plans are often devised by governments or businesses who want to be prepared for anything that could happen. Here there are no such plans.

D: Secondary risks are risks that come about as a result of implementing a risk response. But here in this scenario, risk event has not occurred yet.



There are five inputs to the quantitative risk analysis process. Which one of the following is NOT an input to quantitative risk analysis process?

  1. Risk management plan
  2. Enterprise environmental factors
  3. Cost management plan
  4. Risk register

Answer(s): B

Explanation:

Enterprise environmental factor is not an input to the quantitative risk analysis process. The five inputs to the perform quantitative risk analysis process are: risk register, risk management plan, cost management plan, schedule management plan, and organizational process assets.

Incorrect Answers:
A, C, D: These are the valid inputs to the perform quantitative risk analysis process.



Stephen is the project manager of the GBB project. He has worked with two subject matter experts and his project team to complete the risk assessment technique. There are approximately 47 risks that have a low probability and a low impact on the project. Which of the following answers best describes what Stephen should do with these risk events?

  1. Because they are low probability and low impact, Stephen should accept the risks.
  2. The low probability and low impact risks should be added to a watchlist for future monitoring.
  3. Because they are low probability and low impact, the risks can be dismissed.
  4. The low probability and low impact risks should be added to the risk register.

Answer(s): B

Explanation:

The low probability and low impact risks should be added to a watchlist for future monitoring. Incorrect Answers:
A: The risk response for these events may be to accept them, but the best answer is to first add them to a watchlist.

C: Risks are not dismissed; they are at least added to a watchlist for monitoring.

D: While the risks may eventually be added to the register, the best answer is to first add them to the watchlist for monitoring.



Page 24 of 451



Post your Comments and Discuss ISACA CRISC exam with other Community members:

Fei commented on November 26, 2024
Very good resources
UNITED STATES
upvote

Yingying Li commented on December 02, 2023
Very useful practice tests.
Anonymous
upvote

Stephen commented on August 27, 2023
Can you please share CIMAPRA19-FO2-1 Exam dumps please
Anonymous
upvote

Parsad commented on June 04, 2023
Thank you for the buy 1 get 1 free discount. This helped me a lot. I donot have a lot of money.
INDIA
upvote

Petros commented on May 01, 2023
I could not have passed my certification test without the help of this study guide - highly recommend it!
PORTUGAL
upvote

Bobby commented on January 18, 2022
Passed easily.
UNITED STATES
upvote

Santosh commented on January 29, 2020
Passed my exam today with a score of 798. This is good material.
INDIA
upvote

Arron commented on January 26, 2020
This saved me so much time. The questions and answers are adequate and close to real exam. I like the PDF and its format. Just put it on my iPad and studied while traveling to work. This was my first time using this site and I am pretty happy about their service and price.
GERMANY
upvote

Suresh commented on April 17, 2019
This download is a waste of time . I downloaded the windows app and installed and it is asking to load the test. No documentation provided on how to use the desk top tool. Unable to install on my MAC not Iphone compatible. RE- Admin: Suresh, our website clearly says that the Test Engine software is for Windows only. We have not advertised anywhere in our website saying the Test Engine Software is for MAC as well.
UNITED STATES
upvote