You are the risk professional of your enterprise. Your enterprise has introduced new systems in many departments. The business requirements that were to be addressed by the new system are still unfulfilled, and the process has been a waste of resources. Even if the system is implemented, it will most likely be underutilized and not maintained making it obsolete in a short period of time. What kind of risk is it?

  1. Inherent risk
  2. Business risk
  3. Project risk
  4. Residual risk

Answer(s): B

Explanation:

Business risk relates to the likelihood that the new system may not meet the user business needs, requirements and expectations. Here in this stem it is said that the business requirements that were to be addressed by the new system are still unfulfilled, therefore it is a business risk.

Incorrect Answers:
A: This is one of the components of risk. Inherent risk is the risk level or exposure without applying controls or other management actions into account. But here in this stem no description of control is given, hence it cannot be concluded whether it is an inherent risk or not.

C: Project risk are related to the delay in project deliverables. The project activities to design and develop the system exceed the limits of the financial resources set aside for the project. As a result, the project completion will be delayed. They are not related to fulfillment of business requirements.

D: This is one of the components of risk. Residual risk is the risk that remains after applying controls.
But here in this stem no description of control is given, hence it cannot be concluded whether it is a residual risk or not.



Qualitative risk assessment uses which of the following terms for evaluating risk level?
Each correct answer represents a part of the solution. Choose two.

  1. Impact
  2. Annual rate of occurrence
  3. Probability
  4. Single loss expectancy

Answer(s): A,C

Explanation:

Unlike the quantitative risk assessment, qualitative risk assessment does not assign dollar values. Rather, it determines risk's level based on the probability and impact of a risk. These values are determined by gathering the opinions of experts.
Probability- establishing the likelihood of occurrence and reoccurrence of specific risks, independently, and combined. The risk occurs when a threat exploits vulnerability. Scaling is done to define the probability that a risk will occur. The scale can be based on word values such as Low, Medium, or High. Percentage can also be assigned to these words, like 10% to low and 90% to high.
Impact- Impact is used to identify the magnitude of identified risks. The risk leads to some type of loss. However, instead of quantifying the loss as a dollar value, an impact assessment could use words such as Low, Medium, or High. Impact is expressed as a relative value. For example, low could be 10, medium could be 50, and high could be 100.
Risk level = Probability * Impact Incorrect Answers:
B, D: These are used for calculating Annual loss expectancy (ALE) in quantitative risk assessment. Formula is given as follows:
ALE= SLE * ARO



You are working in an enterprise. Your enterprise is willing to accept a certain amount of risk. What is this risk called?

  1. Hedging
  2. Aversion
  3. Appetite
  4. Tolerance

Answer(s): C

Explanation:

Risk appetite considers the qualitative and quantitative aspects of accepting risks in an organization. The term refers to the type of risks the organization is willing to pursue, as well as amount of risk and the level of risk.

Risk appetite is the amount of risk a company or other entity is willing to accept in pursuit of its mission. This is the responsibility of the board to decide risk appetite of an enterprise. When considering the risk appetite levels for the enterprise, the following two major factors should be taken into account:
The enterprise's objective capacity to absorb loss, e.g., financial loss, reputation damage, etc.
The culture towards risk taking-cautious or aggressive. In other words, the amount of loss the enterprise wants to accept in pursue of its objective fulfillment.

Incorrect Answers:
A, B: Aversion and hedging are related to each other and represents the avoidance of risk within the organization.

D: The acceptable variation relative to the achievement of an objective is termed as risk tolerance. In other words, risk tolerance is the acceptable deviation from the level set by the risk appetite and business objectives.

Risk tolerance is defined at the enterprise level by the board and clearly communicated to all stakeholders. A process should be in place to review and approve any exceptions to such standards.



You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via. email every week. You have agreed and send reports every Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

  1. Configuration management
  2. Communications management
  3. Perform integrated change control process
  4. Project change control process

Answer(s): C

Explanation:

Although this appears to be a simple change the project manager must still follow the rules of the project's change control system.

Integrated change control is a way to manage the changes incurred during a project. It is a method that manages reviewing the suggestions for changes and utilizing the tools and techniques to evaluate whether the change should be approved or rejected. Integrated change control is a primary component of the project's change control system that examines the affect of a proposed change on the entire project.

Incorrect Answers:
A: Configuration management is the documentation and control of the product's features and functions. B: Communications management is the execution of the communications management plan.
D: The project change control process not valid as it's the parent of the integrated change control process, which is more accurate for this question.



Page 90 of 451



Post your Comments and Discuss ISACA CRISC exam with other Community members:

Fei commented on November 26, 2024
Very good resources
UNITED STATES
upvote

Yingying Li commented on December 02, 2023
Very useful practice tests.
Anonymous
upvote

Stephen commented on August 27, 2023
Can you please share CIMAPRA19-FO2-1 Exam dumps please
Anonymous
upvote

Parsad commented on June 04, 2023
Thank you for the buy 1 get 1 free discount. This helped me a lot. I donot have a lot of money.
INDIA
upvote

Petros commented on May 01, 2023
I could not have passed my certification test without the help of this study guide - highly recommend it!
PORTUGAL
upvote

Bobby commented on January 18, 2022
Passed easily.
UNITED STATES
upvote

Santosh commented on January 29, 2020
Passed my exam today with a score of 798. This is good material.
INDIA
upvote

Arron commented on January 26, 2020
This saved me so much time. The questions and answers are adequate and close to real exam. I like the PDF and its format. Just put it on my iPad and studied while traveling to work. This was my first time using this site and I am pretty happy about their service and price.
GERMANY
upvote

Suresh commented on April 17, 2019
This download is a waste of time . I downloaded the windows app and installed and it is asking to load the test. No documentation provided on how to use the desk top tool. Unable to install on my MAC not Iphone compatible. RE- Admin: Suresh, our website clearly says that the Test Engine software is for Windows only. We have not advertised anywhere in our website saying the Test Engine Software is for MAC as well.
UNITED STATES
upvote