You work as a project manager for BlueWell Inc. Your project is running late and you must respond to the risk.
Which risk response can you choose that will also cause you to update the human resource management plan?

  1. Teaming agreements
  2. Crashing the project
  3. Transference
  4. Fast tracking the project

Answer(s): B



FITSAF stands for Federal Information Technology Security Assessment Framework. It is a methodology for assessing the security of information systems.
Which of the following FITSAF levels shows that the procedures and controls have been implemented?

  1. Level 2
  2. Level 3
  3. Level 5
  4. Level 4
  5. Level 1

Answer(s): B



You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events.
Where will you record the mitigation response?

  1. Risk register
  2. Risk log
  3. Risk management plan
  4. Project management plan

Answer(s): A