Which of the following is NOT a typical key challenge for testing in a RAD based development approach?

  1. Re-usable test scripts for (automated) regression testing
  2. Project management and control
  3. No complete requirements specification
  4. Time-boxing

Answer(s): B



View Related Case Study

As a result of the RAD based development approach, the test manager has decided to change the risk mitigation approach. Which test technique might be most appropriate to use?

  1. Decision Table Testing
  2. Boundary Value Analysis
  3. Error Guessing
  4. Exploratory Testing

Answer(s): D



View Related Case Study

The business has asked for a weekly progress report. Which of the following would be appropriate as a measure of test coverage?

  1. Percentage of business requirements exercised
  2. Percentage of planned hours worked this week
  3. Percentage of countries that have test scenarios
  4. Percentage of test iterations completed

Answer(s): A



View Related Case Study

Which one of the following estimation approaches is appropriate at this stage of the project?

  1. Create an estimate based on the function point analysis technique and test point analysis
  2. Create an estimate based on the complexity of the code
  3. Create an estimate based on the credentials of the successful bidder
  4. Create an estimate based on a percentage of the development effort

Answer(s): A