Scenario: "Medical Domain"
You are working as a test manager in the medical domain leading a team of system testers. You are currently working on a major release of the product which gives customers many new features and resolves a number of problem reports from previous releases.

A test log is one of the documents that need to be produced in this domain in order to provide evidence of testing. However, the level of detail of test logs can vary. Which of the following is NOT an influencing factor for the level of detail of the test logs being produced? 1 credit

  1. Level of test execution automation
  2. Test level
  3. Regulatory requirements
  4. Experience level of testers

Answer(s): D



You are about to release a test progress report to a senior manager, who is not a test specialist. Which of the following topics should NOT be included in the test progress report? 1 credit

  1. Product risks which have been mitigated and those which are outstanding.
  2. Recommendations for taking controlling actions
  3. Status compared against the started exit criteria
  4. Detailed overview of the risk-based test approach being used to ensure the exit criteria to be achieved

Answer(s): D



Consider the typical objectives of testing. Which of the following metrics can be used to measure the effectiveness of the testing process in achieving one of those objectives? 1 credit

  1. Average number of days between defect discovery and resolution
  2. Percentage of requirements covered
  3. Lines of code written per developer per day
  4. Percentage of test effort spent on regression testing

Answer(s): B



Considerable attention will be given in this project to defining exit criteria and on reporting back on their status. Which combination of TWO exit criteria from the list would be best to use? 1 credit

I) Total number of defects found
II) Percentage of test cases executed
III) Total test effort planned versus total actual test effort spent
IV) Defect trend (number of defects found per test run over time

  1. (i) and (ii)
  2. (i) and (iv)
  3. (ii) and (iii)
  4. (ii) and (iv)

Answer(s): D



The developers are willing to build a tool that will provide traceability between the source code modules and the test cases that test those modules.
What management concerns should you have with this development effort?

  1. Long term maintenance may not be planned, leaving you with an unsupported tool
  2. The scope of the project is too large and the tool will be too generic to be useful
  3. There are no requirements for this effort so you will be at the mercy of what the developers decide to implement
  4. It is unlikely that the ROI will be achieved

Answer(s): A